The AER proposes the following revisions to make the revised access arrangement proposals acceptable:
Revision 6.1: Make all necessary amendments to reflect the AER’s final decision on the regulatory depreciation allowances for the 2013–17 access arrangement period, as set out in Table 6 .50 and Table 6 .51.
Revision 6.2: Make all necessary amendments to reflect the AER’s final decision on the remaining economic lives as at 1 January 2013, as set out in Table 6 .54.
Operating expenditure (opex) refers to the operating, maintenance and other non-capital costs incurred in providing pipeline services.637 It incorporates labour costs associated with operating the gas distribution network.
The AER is required to assess Envestra's forecast opex to decide whether it is satisfied the forecast opex complies with applicable criteria prescribed by the NGL and NGR.638 This includes that any forecast or estimate must be arrived at on a reasonable basis and represent the best forecast or estimate possible in the circumstances.639
The AER's final decision is not to approve a forecast opex of $328.0 million ($2011) for the 2013–17 access arrangement period for Envestra's Victorian network. The AER instead considers forecast opex of $308.7 million ($2011) reflects a forecast opex that complies with the criteria governing opex and the criteria for forecasts and estimates.640
The differences between the AER's final decision on forecast opex and Envestra's revised opex forecast proposal primarily reflects different views about forecast step changes above base year opex and forecast labour cost escalation.
Table 7 .55 compares the AER's final decision to Envestra's initial and revised proposal for the Victorian network and the AER's draft decision for each year of the 2013–17 access arrangement period.
Table 7.55 Comparison of Envestra Victoria's initial and revised proposals, and AER draft and final decisions ($million, 2011)
The AER's final decision is not to approve a forecast opex of $10.9 million ($2011) for the 2013–17 access arrangement period for Envestra's Albury network. The AER instead considers forecast opex of $10.41 million ($2011) reflects a forecast opex that complies with the criteria governing opex and the criteria for forecasts and estimates.641
The differences between the AER's final decision on forecast opex and Envestra's revised opex forecast proposal primarily reflects different views about forecast step changes above base year opex and forecast labour cost escalation.
Table 7 .56 compares the AER's final decision to Envestra's initial and revised proposal for the Albury network and the AER's draft decision for each year of the 2013–17 access arrangement period.
Table 7.56 Comparison of Envestra Albury's initial and revised proposals, and AER draft and final decisions ($million, 2011)