Planned Sub-Components/Activities
-
Adopt 6 Federal and Regional level software and standards(Unified Billing System-UBS, Trade Registration and License, EMIS, HMIS,HRMS, Acts and Civil Status Registry System etc)
-
Develop and Implement Automation System for Priority 4 Sectors
-
Develop and Implement Portal System for 26 Regional Sectors
-
Deliver the Digital Library System to customer
-
develop 7 different Open source Soft wares (Educational Simulations, Digital Notice board, Online Exam, etc)
-
Repacking 2 Globally available information, Guidelines and knowledge to local needs
-
Implement applications (Fax automation, Kebele automation, PIIMS, Mail server exchange, WIRS) for 5 Regional Sectors and Zone Offices.
-
Accomplishments
-
Adopt 6 Federal and Regional level software and standards(Unified Billing System-UBS, Trade Registration and License, EMIS, HMIS,HRMS, Acts and Civil Status Registry System etc)
As per our plan one application Software’s, Rural Kebele Database Management system taken from Tigray region is customized. For implementation, experts have conducted awareness after installed at Zone, selected Woredas and implement at Keble level.
User manual preparation and piloting at the agency level is carried out. In the same manner rural Kebeles were identified for Kebele database management system implementation in accordance to the criteria (Electric power, office, computer access and the like) set by the agency.
Software’s developed at federal level, like Electronic health management information system, education management system and trade license are also going well
-
Implement Automation System for Priority 4 Sectors
Business Process Reengineering Automation developed for four Bureaus (Education 5 systems, Health 6 systems , Agriculture 6 systems , Labor and Social affairs 2 systems and 3 common systems for all Bureaus totally 22 systems developed for four Bureaus ), automation development is being completed. 3-14 days end user training is conducted by the developer. Currently the automation system is under hosting process.
-
Implement Portal System for 26 Regional Sectors
Regional Portal System consisting of 26 Sectors is completed. End user training is conducted by the developer. Currently the portal is hosted and functional www.amhara.gov.et .
-
Deliver the Digital Library System to customer
Development of digital library system for ANRS Peoples Martyrs Monument Office is developed and enriched by workshop participants. Supplementary documents are produced. Currently, teaching books, different softwares, video, images (figures) are uploaded to the system and is in use.
-
develop 7 different Open source Softwares(Educational Simulations, Digital Notice board, Online Exam, etc)
Development of Attendance Database system is completed. This database is tested in pilot areas, and seen as a solution for time management and it is used for information transfer if the employee is in meeting or out of office. Online exam development is completed and currently installation of exams is being conducted. Educational simulation is completed and submitted for Bureau of Education for comment. BSC automation (BSC Excel) is completed and implemented in the agency. Next budget year it will be scaled up to other sectors. Store Management System, Materials Registration Data base Management System and the like are also completed.
-
Repacking 2 Globally available information, Guidelines and knowledge to local needs
For effective and efficient service delivery and maintenances 103 software Galleries are collected and identified. These software Galleries are organized on the Agency FTP server.
-
Implement applications (Fax automation, Kebele automation, Mail server exchange, WIRS) for 5 Regional Sectors and Zone Offices.
Through field visit and information exchange Applications so far developed and customized are in use. Amhara Region Kebele Data Base (ARKDB) customized from Tigray Region is improved according to the Region context and is completed. Usage manual is developed. Testing in three Woredas has been conducted. Currently expansion is done.
-
Reasons for Deviations (If plans and Accomplishments are Different)
No
|