Lesson learned (design and process): Coordination with parallel initiatives should be attempted designed into the projects from the beginning, not being the sole responsibility of the project manager during implementation.
Component 4: Training and human capital development for the wind energy sector
SAWEP PPG developed 2013/14. Updates and adjustments to SAWEP 2 components, outputs and activities were then identified with key stakeholders prior to and as reported in the Inception Workshop report. The SAWEP Prodoc to be updated accordingly.
SAWEP PPG developed 2013/14. Updates and adjustments to SAWEP 2 components, outputs and activities were then identified with key stakeholders prior to and as reported in the Inception Workshop report. The SAWEP Prodoc to be updated accordingly.
SAWEP 2 budget does not provide, as in SAWEP 1 for reporting costs (e.g. printing) and also not for Miscellaneous expenses (information banners, pamphlets) nor project workshop e.g. catering costs