Capital Works Management Framework Guidance Note Public Works Contracts gn 5



Yüklə 2,1 Mb.
səhifə21/27
tarix20.02.2018
ölçüsü2,1 Mb.
#43156
1   ...   17   18   19   20   21   22   23   24   ...   27

Appendices

Overview



Contents

This section contains the following appendices that supplement the information in the main body of the guidance notes:




Appendix

See Page

A

Comparison of Minor Works Contracts and Traditional Contracts
Outlines the differences between minor works contracts and traditional employer-design contracts.

237

B

Pre-Tender Checklists

Includes a number of checks that the Employer needs to complete before issuing tender documentation.



239

C

Price Variation Calculation under PV2 (Formula Fluctuations Method): Worked Examples
Contains a number of worked examples to illustrate the application of the various price fluctuation formulae.

245

D

Department of Finance Guidelines on Methods of Measurement
Details of Department of Finance approved method of measurement (Building) and amendments to approved methods of measurement (Civil).

254


Appendix A: Comparison of Minor Works Contracts and Traditional Contracts

Comparison Table





The Minor Works Contract for the Provision of Building and Civil Engineering Works Designed by the Employer (the minor works contract / contract No 5) is similar in most respects to the Public Works Contract for the Provision of Building Works ( Civil Engineering Works) Designed by the Employer (the traditional contracts No. 1 and No. 3). The differences are summarised in the table below.




Clause in Traditional Contracts*

Differences in the Minor Works Contract







1.6 Parent Company Guarantee

There is no requirement on the Contractor under the contract to provide the parent company guarantee by the Starting Date.







2.7 Legal Opinion

There is no clause requiring the provision of a legal opinion relating to a Contractor who is not an individual or company incorporated in Ireland.







3.3.1 Insurance of Employer’s Property

Part 1D of the Schedule does not provide for an additional list of Employer’s property which the Contractor must insure.







3.9.3 Extensions and Additional Requirements in the Schedule

Part 1D of the Schedule does not provide scope for the Employer to specify extensions and additional requirements in relation to insurances.







3.9.9 Owner-controlled Insurance

Does not provide for the insurance programme to be owner-controlled.







4.2.1(2) Supervisor

The Contractor must appoint a supervisor to the site, but the supervisor does not need to be appointed on a full time basis.







4.8 Value Engineering

Does not include a procedure for value engineering.







4.9 Programme

The content requirements for the programme are not as detailed. However, if more details are required they can be set out in the Works Requirements.







4.10 Progress Reports

The content requirements of progress reports are not as detailed.




*Clause numbers refer to the Contract Conditions.

Continued on next page

Comparison Table, Continued




Clause in Traditional Contract

Differences in the Minor Works Contract

5.4 Sub-contractors and Specialists

If the Contractor intends to sub-contract part of the works, other than in accordance with the Contract, the Contractor should obtain the consent of the Employer’s Representative (ER).

7.9 Access

Does not contain the traffic obligations relating to the transport of large loads.

7.10 Condition of Site on Completion

There is no such clause relating to removing Contractor’s Things

7.11 Working Times

There is no clause relating to the site working times of the Contractor’s personnel.

8.5 Rejection of Defects

Does not contain a mechanism allowing the ER to reject the works if a defect deprives the Employer of substantially the whole benefit of the Works.

9.4 Programme Contingency

There is only one threshold (stated in the Schedule) in relation to the number of site working days’ delay.

  • If the delay is less than the threshold, there shall be no extension to the Date for Substantial Completion.

  • If the delay exceeds the threshold, then only those days by which it exceeds the threshold may be added to the Date for Substantial Completion.

This clause does not apply to extensions of time resulting from delay events which are not also compensation events.

9.7 Taking Over Part of the Works

Does not contain a provision relating to the take-over by the Employer of part of the works before Substantial Completion.

10.7.3 Delay Costs

Makes no provision for adjustment of the Contract Sum in the case of a compensation event resulting in seven or more consecutive non-working days leading to an extension of the Date for Substantial Completion.



Yüklə 2,1 Mb.

Dostları ilə paylaş:
1   ...   17   18   19   20   21   22   23   24   ...   27




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin