An estimated total of four years is envisaged for the construction of the KAHEP. A tentative construction schedule is presented in Table 2.3.
Table 2.3: Implementation Schedule of KAHEP
SN
|
Construction Activities
|
Years
|
1
|
2
|
3
|
4
|
1st qtr
|
2nd qtr
|
3rd qtr
|
4th qtr
|
1st qtr
|
2nd qtr
|
3rd qtr
|
4th qtr
|
1st qtr
|
2nd qtr
|
3rd qtr
|
4th qtr
|
1st qtr
|
2nd qtr
|
3rd qtr
|
4th qtr
| -
|
Pre-construction works (access roads improvement and contractual works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| -
|
Construction mobilization
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| -
|
Diversion facilities
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| -
|
Weir and barrage
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| -
|
Intake structure and settling basin
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| -
|
River Training works at headworks
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| -
|
Tunnel and surge shaft
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| -
|
Powerhouse and tailrace
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| -
|
Hydro mechanical parts
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| -
|
E & M equipment
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| -
|
Switchyard
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| -
|
Testing and commissioning
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Source: UFSR 2011