Implementation Schedule


An estimated total of four years is envisaged for the construction of the KAHEP. A tentative construction schedule is presented in Table 2.3.

Table 2.3: Implementation Schedule of KAHEP

SN

Construction Activities

Years

1

2

3

4

1st qtr

2nd qtr

3rd qtr

4th qtr

1st qtr

2nd qtr

3rd qtr

4th qtr

1st qtr

2nd qtr

3rd qtr

4th qtr

1st qtr

2nd qtr

3rd qtr

4th qtr



Pre-construction works (access roads improvement and contractual works



















































Construction mobilization



















































Diversion facilities



















































Weir and barrage



















































Intake structure and settling basin



















































River Training works at headworks



















































Tunnel and surge shaft



















































Powerhouse and tailrace



















































Hydro mechanical parts



















































E & M equipment



















































Switchyard



















































Testing and commissioning

















































Source: UFSR 2011

    1. Yüklə 3,88 Mb.

      Dostları ilə paylaş:
1   ...   9   10   11   12   13   14   15   16   ...   53




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin