The cost for environmental monitoring of the project is presented in Table 9.2. The costs included in this section present only the costs where KAHEP management is responsible for the compliance and impact monitoring through an instrumental monitoring. The costs of the other monitoring activities through technical support staff at site are included in the environmental management costs of the project. The costs where contractor is responsible for monitoring are part of the project civil costs and not included here.
Table 9.2: Environmental Monitoring Cost
SN
Monitoring Items
Estimated Cost (NRs.)
Remarks
A
Pre- Construction Phase
1
Air Quality (TSP and PM 10)
450,000.00
2
Noise
75,000.00
3
Water Quality including microbiology and temperature
500,000.00
4
Monitoring of Landslides and slide erosion, Land pollution,
65,000.00
5
Monitoring of Springs and water holes and Structural conditions of built structures
Estimated NRs 715,000.00 has already included in Mitigation.
6
Monitoring of Forest ecology and Wildlife
130,000.00
7
Aquatic Life (fish study of Kabeli and Tamor River)
450,000.00
8
Community use of water and riverine areas in Tamor River
150,000.00
Sub-Total A
1,820,000.00
Excluding items included in mitigation
B
Construction Phase
1
Air Quality (TSP and PM 10) twice a year for 4 years
3,600,000.00
2
Noise level twice a year for 4 years
600,000.00
3
Water Quality including microbiology and temperature for 4 years
400,000.00
4
Aquatic Life twice a year for 4 years
500,000.00
5
Support for other construction phase monitoring as per Table 8.13
1,200,000.00
Additional cost to KAECDU
Sub-Total B
6,300,000.00
C
Operation Phase
1
Water quality in the operation camp (twice a year for 30 years)
1,500,000.00
2
Water Quality (River) Twice a year (November, April) for first 5 years
500,000.00
3
Noise level
75,000.00
4
Springs and water holes (once a year for first 5 years)