Table 2.5 Guidelines for selecting design floods (14)
S. No.
|
Structure
|
Recommended design flood
|
|
|
|
1.
|
Spillways for major and medium
|
(a) PMF determined by unit hydrograph and
|
|
projects with storage more than 60 Mm3
|
probable maximum precipitation (PMP)
|
|
|
(b) If (a) is not applicable or possible, flood-
|
|
|
frequency method with T = 1000 years to 5000
|
|
|
years
|
|
|
|
2.
|
Permanent barrage and minor dams
|
(a) SPF determined by unit hydrograph and
|
|
with capacity less than 60 Mm3
|
standard project storm (SPS) which is usually
|
|
|
the largest recorded storm in the region
|
|
|
(b) Flood with a return period of 100 years.
|
|
|
(a) or (b) whichever gives higher value.
|
|
|
|
3.
|
Pickup weirs
|
Flood with a return period of 100 or 50 years
|
|
|
depending on the importance of the project.
|
|
|
|
4.
|
Aqueducts
|
|
|
(a) Waterway
|
Flood with T = 50 years
|
|
(b) Foundations and free board
|
Flood with T = 100 years
|
|
|
|
5.
|
Project with very scanty or inadequate
|
Empirical formulae
|
|
data
|
|
|
|
|
The PMF is used for structures such as dams, spillways etc. whose failure would result in huge loss of life and property. Table 2.6 provides guidelines for this purpose (15).
Table 2.6 Design flood for dams
-
Size/class of dam
|
Gross storage
|
Hydraulic Head
|
Design Flood
|
|
(Mm3)
|
(m)
|
|
Small
|
0.5 to 10.00
|
7.5 to 12.0
|
100 – year flood
|
Medium
|
10.0 to 60.00
|
12.0 to 30.0
|
SPF
|
Large
|
more than 60.0
|
more than 30.0
|
PMF
|
|
|
|
|
90 IRRIGATION AND WATER RESOURCES ENGINEERING
EXERCISES
-
There are five rain gauges uniformly spread in a small watershed. The depths of rainfall observed at these rain gauges and the area of Theissen polygons for the corresponding rain gauges are as follows :
-
Rain gauge no.
|
1
|
2
|
3
|
4
|
5
|
Rainfall depth (cm)
|
47.3
|
46.4
|
43.8
|
52.3
|
48.5
|
Area of Theissen polygon (1000 m2)
|
95
|
102
|
98.67
|
80.52
|
85.38
|
Determine the average depth of precipitation.
-
The amounts of rainfall for 6 successive days on a catchment were 2, 5, 7, 8, 5, and 1 cm. If the φ-index for the storm is 4 cm/day, find the total surface runoff.
-
The normal annual precipitation at four rain gauge stations is 120, 100, 84, and 120 cm, respec-tively. During a particular storm the rain gauge at station A became non-functional. The rainfall depths recorded at B, C, and D are respectively, 10, 7 and 11 cm. Estimate the rainfall depth at station A during the storm.
-
In a drainage basin, there exist 6 rain gauges, and average rainfall at these stations is 106, 91, 65, 55, 62, and 48 cm. Determine if these rain gauges are adequate to give reliable measure-ments of rainfall with an error of less than 10% ? If not, how many additional rain gauges are needed ?
-
The ordinates of three unit hydrographs derived from separate storms of 4-hour rains each are as follows :
-
Hours
|
Storm 1
|
Storm 2
|
Storm 3
|
Hours
|
Storm 1
|
Storm 2
|
Storm 3
|
|
|
|
|
|
|
|
|
0
|
0
|
0
|
0
|
8
|
135
|
165
|
214
|
1
|
115
|
20
|
16
|
9
|
100
|
125
|
164
|
2
|
370
|
120
|
57
|
10
|
70
|
85
|
121
|
3
|
505
|
353
|
173
|
11
|
45
|
55
|
90
|
4
|
395
|
460
|
335
|
12
|
27
|
30
|
60
|
5
|
315
|
400
|
442
|
13
|
15
|
15
|
35
|
6
|
240
|
300
|
400
|
14
|
10
|
3
|
16
|
7
|
175
|
215
|
283
|
15
|
0
|
0
|
0
|
|
|
|
|
|
|
|
|
Find the average unit hydrograph.
-
The observed stream discharges resulting from a storm of 3-hr duration are as follows :
-
Hour
|
Day 1
|
Day 2
|
Day 3
|
Hour
|
Day 1
|
Day 2
|
Day 3
|
|
|
|
|
|
|
|
|
3 a.m
|
550
|
4500
|
1800
|
3 p.m.
|
8000
|
2600
|
1000
|
6 a.m
|
500
|
3900
|
1600
|
6 p.m.
|
7000
|
2300
|
900
|
9 a.m
|
6000
|
3400
|
1400
|
9 p.m.
|
6000
|
2000
|
800
|
Noon
|
9500
|
3000
|
1200
|
Mid-night
|
5200
|
1800
|
700
|
|
|
|
|
|
|
|
|
The drainage area of the stream is 2000 km2. Derive the unit hydrograph assuming constant base flow of 500 m3/s.
-
For storm 1 of Exercise 2.5, obtain the S-hydrograph and derive the 2-hr and 6-hr unit hydrographs.
REFERENCES
-
Mays, L.W., Water Resources Engineering, John Wiley and Sons Inc., Singapore, 2004.
-
Kurino T. (1997), A Satellite Infrared Technique for Estimating ‘‘deep/shallow’’ precipitation, Adv. Space Res., Vol. 19, No. 3, pp. 40-63.
3. ...... Guide to Hydrometeorological Practices, 3rd edition, WMO no. 168, Geneva, 1974.
4. ......Bureau of Indian Standards (IS: 8389-1983); IS Code of Practice for Installation and Use of Rain gauges and Recording.
-
Kohler, M.A., Double—Mass Analysis for Testing Consistency of Records and for Making Required Adjustments, Bulletin of American Meteorological Society, Vol. 30, no. 5, May 1949.
-
Dhar, O.N. and A.K. Kulkarni, Estimation of Probable Maximum Precipitation for Some Selected Stations in and Near Himalayas, Proc. of National Symposium on Hydrology, Roorkee, India 1975.
-
Weisner, C.J., Hydrometeorology, Chapman and Hall, London, 1970.
-
Subramanya, K., Engineering Hydrology, Tata McGraw-Hill Publishing Company Ltd., New Delhi, 1994.
-
Linsley R.K. (Jr.), Kohler, M.A., and Paulhus, J.L.H., Hydrology for Engineers, McGraw-Hill Book Co. 1988.
-
Sherman, L.K., Streamflow from Rainfall by the Unit-Graph Method, Engg. news Record, Vol. 108, pp. 501-505, 1932.
11. ...... Flood Estimation Report for Lower Godavari (sub-zone 3F), Design Office report no. 3/1980, Directorate of Hydrology (Small Catchments), Central Water Commission, New Delhi, 1980.
12. ...... Flood Estimation Report for lower Narmada and Tapi (sub-zone 3B), Design Office report no. M/5//1981, Directorate of Hydrology (Small Catchments), Central Water Commission, New Delhi, 1980.
13. ...... Flood Estimation Report for Mahanadi (sub-zone 3D), Design Office report no. LNT/4/1981, Directorate of Hydrology (Small Catchments), Central Water Commission, New Delhi, 1982.
14. ...... Estimation of Design Flood Peak, Report no. 1/73, Central Water Commission, New Delhi 1973.
15. ...... IS: 11223-1985—Guidelines for fixing Spillway Capacity, Bureau of Indian Standards.
Dostları ilə paylaş: |