1 INTRODUCTION 9
1.1 Purpose of guidelines 9
1.2 Definitions of minimum norms and standards 10
1.3 Project development life cycle 11
2 LEGISLATION AND POLICY 13
3 INSTITUTIONAL ARRANGEMENTS 14
3.1 Introduction 14
3.2 Deciding on and contracting with a water services provider 14
3.3 Bylaws and other requirements 15
4 PLANNING 16
4.1 Introduction 16
4.2 National reference plan 16
4.3 Water services development plan 18
4.4 Feasibility studies and technical reports 18
5 DESIGN CRITERIA 27
5.1 Introduction 27
5.2 Summary of design and planning criteria 27
5.3 Water availability 29
5.4 Power availability and alternative pump drives 29
5.5 Guidelines for economic optimisation of pump - pipeline sizing 29
5.5.1 Economic analyses 30
5.5.2 Pump and pipe sizing for small borehole schemes 30
6 DESIGN REPORT, DRAWINGS AND SPECIFICATIONS 32
6.1 Introduction 32
6.2 Design report 32
6.3 Sustainability 33
6.4 Drawings 33
6.5 Standard drawings 34
6.6 Special drawing requirements and operating and maintenance manuals 35
6.7 Design specifications 35
7 BOREHOLES 36
7.1 Borehole development steps 36
7.2 Borehole pumps 37
7.3 Borehole monitoring and other equipment 38
8 DAMS AND WEIRS 40
8.1 Dams 40
8.2 Weirs 40
8.3 Approved professional engineer 41
8.4 Outlet works of dams and weirs 41
8.4.1 Depth of water draw off 41
8.4.2 Outlet pipe systems 42
8.4.3 Intake entrance 42
8.4.4 Control valves for outlet works 42
8.4.5 Maintenance cranes 45
8.4.6 Screening of intake works 46
9 WATER TREATMENT WORKS 47
9.1 General 47
9.2 Potable water quality 47
9.3 Selection of appropriate treatment process 47
9.4 Recommended loading rates and design parameters for water treatment process units 47
9.5 Automation 48
9.6 Structural considerations 48
9.7 Accessibility 48
9.8 Specifications 49
10 PUMP STATIONS 50
10.1 Introduction 50
10.2 Pump selection 50
10.3 Pump standby capacity 51
10.4 Power requirements for pumps 51
10.5 Pump control 51
10.6 Pump station building 52
10.7 Pumpline components 53
10.7.1 Baseplates 53
10.7.2 Pumps 53
10.7.3 Pump coupling 54
10.7.4 Pump components 54
10.7.5 Motors 54
10.7.6 Pumpset speed 54
10.7.7 Switchgear enclosures: 54
10.7.8 Valves 54
10.7.9 Instrumentation and protection 55
10.7.10 Control panel 56
11 LOW VOLTAGE ELECTRICAL EQUIPMENT 58
11.1 General guidelines 58
11.2 Design report 58
11.3 Important aspects to consider 58
11.4 Maximum voltage 59
11.5 Metering points 59
11.6 Motors 59
11.7 Power cables 59
11.8 LV switchboards and motor control 59
11.8.1 Construction 59
11.9 Switchgear 60
11.9.1 Circuit breakers 60
11.9.2 Isolators 60
11.9.3 Contactors 60
11.9.4 Switch gear general 61
11.10 Motor protection 61
11.11 Indication and instrumentation 61
11.12 Control 62
11.12.1 General 62
11.12.2 Local control 62
11.13 Power factor correction 62
11.14 Earthing 63
11.15 Lightning protection 63
11.16 Conduit wire ways and conduit 63
11.16.1 Conduit 63
11.16.2 Wire ways (conduit and trunking) 63
11.16.3 Cable ways 65
11.16.4 Switches and socket outlets 65
11.16.5 Wiring 65
11.17 Lighting, luminaires and masts 66
11.17.1 Lighting 66
11.17.2 Luminaires 66
11.17.3 High masts 66
11.18 Standby generators 66
12 TELEMETRY 67
12.1 Maintenance 67
12.2 General guidelines 67
12.3 Typical system configuration 67
12.4 Transducers and field instrumentation 68
12.4.1 General 68
12.4.2 Technical requirements 68
12.4.3 Back up requirements 68
12.4.4 Compatibility 68
12.5 Cabling 69
12.5.1 Power cables 69
12.5.2 Data cables 69
12.6 Communication system 69
12.6.1 Transmitter and receivers 69
12.6.2 Masts and antennas 70
12.7 Control systems 70
12.7.1 Control modes 70
12.7.2 Man machine interface 71
12.8 Power supplies 71
12.9 Lightning protection and earthing 72
12.10 Documentation and training 72
12.11 Spares 72
13 PIPELINES 74
13.1 General 74
13.2 Design capacity 74
13.3 Pipeline materials 74
13.4 Pipeline velocities 75
13.5 Pipe friction factors 76
13.6 Depth of pipe cover 76
13.7 Vacuum pressures 76
13.8 Cover 76
13.9 Trench width 77
13.10 Bedding and backfill (including material) 77
13.11 Slope 77
13.12 Meters 77
13.13 Delivery point 77
13.14 Pipe markers 77
13.15 Air release and air intake valves 78
13.16 Scour valves 78
13.17 Isolating valves 78
13.18 Valve chambers 78
13.19 Pressure control valves 79
13.20 Thrust blocks and anchors 79
13.21 Structural design 79
13.22 Corrosion protection 80
13.23 Couplings 80
13.23.1 Rigid couplings/joints 80
13.23.2 Flexible couplings 82
13.24 Fittings 82
13.24.1 Reducers / diffusers and inlets 82
13.24.2 Bends 83
13.24.3 Dividers 83
13.24.4 Puddle or thrust flanges 83
13.24.5 Reinforced specials 83
13.25 Pipeline specifications 84
14 RESERVOIRS 85
14.1 Storage 85
14.2 Storage for small ground water schemes 85
14.3 Design 85
14.4 Materials 86
14.5 Metering 86
14.6 Level control and indication 86
14.7 Position 86
14.8 Break pressure tanks 86
15 STAND PIPES, YARD TANKS AND OTHER CONSUMER CONNECTIONS 88
15.1 Stand pipes 88
15.2 Yard tanks 88
15.3 Valves 88
15.4 Pressure 88
15.5 Minimum flow 89
15.6 Coverage 89
15.7 Walking distance 89
16 VENTILATED IMPROVED TOILETS 90
16.1 Introduction 90
16.2 DefinitionS 90
16.3 Operating principles 91
16.4 Material 92
16.4.1 Concrete 92
16.4.2 Cover slab 92
16.4.3 Pedestal 92
16.4.4 Superstructure 93
16.4.5 Vent pipe 93
16.4.6 Fly screen 93
16.5 Design and construction of a VIP toilet 93
16.5.1 Pit 93
16.5.2 Location 95
16.5.3 Lining 95
16.5.4 Collar 95
16.5.5 Cover slab 96
16.5.6 Pedestal and toilet seat 96
16.5.7 Superstructure 97
16.6 Ventilation 98
16.6.1 General 98
16.6.2 Vent pipe 98
16.6.3 Fly screen 98
16.6.4 Hand-wash facility 99
16.7 Ground water contamination risk associated with a VIP toilet 99
17 STAFF, HOUSING, LABORATORIES, AND OTHER FACILITIES 101
17.1 Staff requirements for water supply schemes 101
17.2 Housing requirement for water supply schemes 103
17.3 Laboratories, offices and other facilities 104
17.4 Non-fixed assets 107
18 TENDER PROCEDURES 108
18.1 Limitations 108
18.2 Steps in the tendering process 108
18.3 Pre- tender stage 109
18.4 Draft tender documents 109
18.4.1 Compilation of draft tender document 109
18.4.2 Standard format of a DWAF tender document 110
18.4.3 Departmental tender and contract forms (C-forms) 111
18.4.4 Departmental formats 113
18.4.5 Standard proformas 113
18.4.6 Other proformas 113
18.4.7 Final tender document 114
18.5 Tender procedure 114
18.6 Tender stage 115
18.6.1 Site inspection 115
18.6.2 Extension of tender period 115
18.6.3 Adjudication of tenders 115
18.6.4 Acceptance of a tender 116
18.6.5 Sureties and insurances 116
18.6.6 Signing of the contract 116
18.6.7 Award meeting 117
18.7 Mechanical tender preparation guidelines 117
18.7.1 Document preparation - broad outline 117
18.7.2 Specific points to be noted 118
18.8 Electrical tender 118
18.9 Procurement of a professional team 119
19 CONTRACT ADMINISTRATION 120
19.1 Payment certificates 120
19.2 Correspondence 121
19.3 Estimated costs 121
19.4 Variation orders 121
19.5 Co-ordination 122
19.6 Construction reports 122
19.7 Inspections 122
19.7.1 Civil works 122
20 REPORTING ON OPERATIONS 125
20.1 Annual scheme audit and water balance 125
21 CONTENTS OF FOLDERS 126
21.1 Legal and policy folder 126
21.2 Institutional folder 126
21.3 Planning folder 126
21.4 Design specifications folder 126
21.5 SANS folder 126
21.6 Drawing folder 127
21.7 Procurement folder 127
21.8 Sanitation folder 127
21.9 Ground water folder 127