12.6WP 4000: Scientific roadmap
PROJECT: CHARMING PHASE:
|
WP: 4000
|
WP Title: Scientific roadmap
Company: INGV
WP Manager: S. Salvi
Start Event: PM5 Planned Start Date: KO+15
End Event: FR Planned Finish Date: FR
|
Sheet 1 of 1
Issue Ref: 1
Issue Date: 05/11/2013
|
Inputs:
-
Project documentation (RB, ATBD, VR)
Tasks:
-
Collect a set of reccommendations concerning measurement techniques and modeling approaches
-
Collect feedback from scientists and institutions who accessed the generated experimental datasets
-
Define a scientific development strategy
-
Define requirements for a transition to operational activities
-
Prepare the SR document
Outputs:
|
|
12.7WP 5000: Project management
PROJECT: CHARMING PHASE:
|
WP: 5000
|
WP Title: Project management
Company: INGV
WP Manager: J.P. Merryman Boncori
Start Event: KO Planned Start Date: KO
End Event: FR Planned Finish Date: FR
|
Sheet 1 of 1
Issue Ref: 1
Issue Date: 05/11/2013
|
Inputs:
-
This proposal; project activities.
Tasks:
-
Generate the Project Management deliverables
Outputs:
-
Project management deliverables listed in Table of this proposal
|
|
12.8Schedule
The proposed project schedule is given in Figure .
The milestone meetings are reported in orange.
The different colours represent the involvement of the different science teams. The numbers provided to the right represent approximate person month involvements.
A tentative KO date is provided, assuming acceptance of the proposal (if awarded) within 6 months from the closing date of the ITT.
Figure : Project Schedule Gantt Chart
12.9Meetings
A meeting plan fully compliant with that proposed in the SoW is given in Table .
All progress meetings shall be carried out via teleconference.
|
Participants
|
INGV
|
IREA
|
Meeting
|
ID
|
Place
|
Time
|
|
|
Kick Off Meeting
|
KO
|
Teleconf.
|
KO
|
S. Salvi, G. Pezzo, J.P. Merryman Boncori, R. Devoti, C. Meletti, V. D'Amico
|
G. Fornaro
|
Mid-Term Review
|
MTR
|
INGV Rome
|
KO + 9 months
|
Final Review
|
FR
|
ESA/ESRIN
|
KO + 18 months
|
Table Scheduled milestone meetings
12.10List of deliverables
A list of deliverables fully compliant with the SoW is given in Table .
Activity
|
Id
|
Deliverable
|
Scheduled delivery
|
Scientific Requirement Consolidation
|
D1
|
Requirement Baseline (RB)
|
PM1 (KO+3)
|
Dataset Collection
|
D2
|
Dataset
|
D3
|
Dataset User Manual
|
Development and Validation
|
D4
|
Algorithm Theoretical Basis Documents (ATBD)
|
MTR (KO+9)
|
D5
|
Product Validation Report (VR)
|
Prototype Demonstration and Impcat Assessment
|
D6
|
Experimental Dataset
|
PM5 (KO+15)
|
D7
|
Updated Dataset User Manual
|
D8
|
Impact Assessment Report (IAR)
|
Scientific Roadmap
|
D9
|
Scientific Roadmap (SR)
|
FR (KO+18)
|
Management
|
D10
|
Final Report (for public access)
|
D11
|
Executive summary
|
D12
|
Project Management Plan
|
KO + 1
|
|
Monthly progress reports
|
At least one week in advance of the meeting
|
|
|
Meeting minutes
|
Within 2 weeks following the meeting
|
|
|
Meeting preparation material (e.g. Agenda, hand-outs)
|
|
Promotion
|
|
Project website setup and maintainance;
Publications (including at least one paper to an international peer-reviewed journal);
Presentation of project results in national and international conferences;
Promotion of project results with relevant scientific and operational communities
|
|
Table List of deliverables