b) Continuation of the current situation, i.e. Mut WPP is not built.
Sub-step 1b. Consistency with mandatory laws and regulations
Both alternatives are (building or not building the project activity) in compliance with the following identified applicable mandatory laws and regulations:
(1) Electricity Market Law24
(2) Law on Utilization of Renewable Energy Resources for the Purpose of Generating Electricity Energy25
(3) Environment Law26
Table : Project Implementation Schedule
Date (DD/MM/YYYY)
|
Activity
|
02/01/2013
|
Board Decision Date
|
05/02/2013
|
“EIA is not Required” decision for 50 MW (16*3mw+1*2mw)
|
27/03/2013
|
Issuance of the License
|
29/07/2013
|
Agreement with Carbon consultant (Lifenerji)
|
23/08/2013
|
Local Stakeholder Meeting
|
25/10/2013
|
Approval letter of “EIA is not required decision” by Provincial Directorate of Environment and Urbanism for 52.8 MWm/50 MWe (16*3,3MW) capacity.
|
28/03/2014
|
Loan Proposal Date
|
17/04/2014
|
Assessment of the Energy production of the Proposed Mut wind farm
|
29/05/2014
|
Notice to Proceed of the Agreement with Equipment provider (project start date)
|
01/06/2014
|
Date for start of construction
|
01/07/2015
|
Planned start date of operation
|
According to Turkish regulations, to get necessary permits for further project implementation, license issued by EMRA is required. Hence, issuance of license cannot be considered as ‘Project Start Date’ but a prerequisite to proceed for further project development activities. Notice to proceed date of electromechanical equipment contract is set to be project starting 29.05.2014. From above Implementation Schedule it can be seen that Mut after having license started to analysis of VER and decided to get consultancy for VER development, much before planned construction starting date.
Aforementioned project implementation schedule shows us that Mut started to consideration of VER from the beginning of the project implementation and VER Revenue has decisive impact on decision of proceeding to the project.
In the following, the investment analysis is applied to clearly demonstrate that the project activity is unlikely to be financially/economically attractive without the revenue from the sale of VERs.
Dostları ilə paylaş: |