The authorization is issued by the National Commission for Nuclear Activities Control (NCNAC) if the requirements for building, endowment with equipment and specialized personnel and the adequate activity organization are fulfilled according to the specified regulations, as shown in Annex 1 of this EMP.
4.3Operational phase
All of the permits which the developer was required to obtain so as to be granted the urbanization permit will need to be kept up-to-date and any re-application made before the relevant permit expires.
All conditions upon which the permit was granted must be complied with.