01413 Details of Schedule
The schedule to be prepared graphically shall indicate the sequence of work, interdependence of activities, cash flow and other pertinent data as listed hereunder and as directed by the Engineer.
Period of mobilization
Start and completion dates of the various trade classified into sections of work including the following.
Submittals of samples & shop drawings.
Order and delivery to site of materials.
Fabrication and installation of materials.
Earliest and latest start and finish date of each activity including float.
Final testing.
Demobilization.
Monetary value associated with start up to completion of works to enable the determination of Contractor's cash flow and Investors budget allocation.