01414 Review of Schedules
Construction schedule shall be prepared and submitted to the Engineer within 20 days of instruction to proceed with the work and in any case not later than the end of the mobilization period. Consideration shall be given to the requirement of the review of the schedule by the Engineer and re-submittal prior to the end of mobilizing period.
Construction Schedule shall be reviewed as instructed by the Engineer at intervals of not more than three months during the Contract implementation period.