0142 Project Meetings
Periodic weekly, monthly and quarterly reports shall be submitted by the Contractor indicating the progress of works.
The monthly progress shall indicate: -


  • The activities carried out in the month and the total to date including value of work.

  • Problems encountered, affected portions of work and their effect on sequential activities.

The Quarterly report shall indicate:-




  • The activities carried out in the quarter and the total to date including value of work.

  • The comparative effect of the activities to the proposed schedule.

  • The problems encountered and their effect on the succeeding work and over all completion time.

  • The validity of the float proposed in the schedule.

  • Review of the Schedule of work.


Yüklə 475,5 Kb.

Dostları ilə paylaş:
1   ...   10   11   12   13   14   15   16   17   ...   249




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin