124 EXECUTION
1241 General
Materials shall be prepared, mixed and applied in strict conformity with the manufacturer's instructions and as approved by the Engineer.
Materials shall be well stirred before application to produce a mixture of uniform density as required during the application.
No painting shall be carried out when rain, fog, condensation is likely to occur, the relative humidity exceeds 85% or the surface to receive paint or primers is damp.
1242 Surface Preparation & Paint Application
12421 General
All work on which painting is to be applied shall be inspected for satisfactory installation to enable painting to start.
Surfaces to receive paint shall be cleaned of all oil, grease, and loose and powdery material. Surfaces to receive paint shall be sufficiently dried before the application of the paint.
All removable items fixed on surfaces to receive paint, but not receiving paint shall be removed before application and re-installed after completion of work.