031323 Gauging and Mixing

Ready mixed concrete shall be batched, mixed and transported in accordance with ASTM C94.


Concrete produced by on site batching and mixing shall conform to the requirement hereunder. Measurement of volume of aggregate shall be made in impervious gauge boxes or containers of accurate size, to a predetermined uniform depth without compacting. The measurement of aggregates by weight shall be made in an approved weight batch. The weight of aggregates shall be as to produce the same mix as produced by volume batching.
Allowance for the water content of the aggregates must be made. The concrete shall be mixed in an approved mechanical batch mixer. Mixing shall continue until there is a uniform distribution of the materials and the mass is uniform in colour and consistency but in no case shall the mixing continue for less than two minutes after adding water. The volume of concrete in any batch shall not exceed the rated capacity of the mixer.
Concrete shall be proportioned and produced to have the limits of slump as shown in the Concrete class section of this Specification." The slump may be varied from the limits as given in the Specification provided approval for such variation is given by the Engineer.

Hand mixing of concrete shall not be done. If the situation makes hand mixing unavoidable, the cement content of the concrete in the mix shall be increased by 10%.


The whole of the mixed batch shall be removed before materials for fresh batch enter the mixer. On cessation of concreting, including all stoppages exceeding 20 minutes, the mixer handling plant and tools shall be washed with water.
Mixed concrete shall not be modified by the addition of extra water or cement or otherwise, in order to facilitate handling or for any other purpose. Additives to improve workability may be used only with prior approval.
The consistency of the concrete shall be controlled by direct measurement of the water content, making allowance for any water in the aggregate. The limits to slump as given in the concrete class section of this Specification shall be used for control purposes.
Admixtures shall be used as directed by manufacturers.
Aggregates in hot weather shall be sprayed with water before mixing to ensure that, the temperature of the aggregate and water mix does not exceed 32 degree centigrade.

Yüklə 475,5 Kb.

Dostları ilə paylaş:
1   ...   39   40   41   42   43   44   45   46   ...   249




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin