Cost-effectiveness dictates: eventually as many instruments as possible
Start in as complementary a mode as possible
Choice
start with 5 MW LP with:
20, and eventually maybe 35 - 40 instruments
As many ancillary and science facilities as affordable
Ready to operate in ‘industry-mode’ too: access mode (financial, time), IP arrangements, demonstration experiments, standardised procedures, etc.)
and as much as possible upgradeable to:
More power
More target stations (SP, LP, low power dedicated TSs
Costs
~1.3 B€2008 investment; 110 M€2008 /y operating.
Design of ESS accelerator was completed in 2002-03, and at that moment considered the best mix between NC technology and SC technology.
Design of ESS accelerator was completed in 2002-03, and at that moment considered the best mix between NC technology and SC technology.
Many relevant developments; several linac projects ongoing; SNS completed.
Completion of baseline engineering, including modifications to optimise cost-performance ratio, were always assumed to take up to 2 years and cost ~ 30M€.
Obvious areas for consideration in design review:
SC cavities below 400 MeV? How low?
Higher gradients per cavity, but high beam current poses limitations
Is one H+ ion source possible? Is it desirable to avoid funnel (front end intensity limited)? One source and 2 GeV?
Frequencies: CERN or DESY frequencies? Yet components will differ due to high beam current, long pulses and low rep rate, necessary for optimal neutron production
Be careful about beam quality, impact on upgradeability, costs, etc.
SNS shows: engineering of liquid Hg target is feasible
Radiation damage to container is limited (LAMPF beam dump, PSI’s liquid PbBi target accumulated as much irradiation as months operation of ESS target; SNS target does extremely well)
What about pitting? SP targets above 2 MW or so seriously affected. There may be solutions (e.g. injecting He bubbles) but 5 MW SP target was too optimistic, at least poses serious risks
Appreciate radical difference between SP and LP target
SP: 23 kJ proton pulse deposited in 1 μs ~ 20 GW instantaneous power (20 x Niagara Falls!)
LP: 300 kJ proton pulse deposited in 2 ms ~ 150 MW (same as HFIR)
Nature of pitting problem
Nature of pitting problem
Almost all proton pulse energy deposited as heat in target Temperature jump of irradiated volume Pressure jump, as heat has to be absorbed in constant volume (inertia of Hg doesn’t allow fast thermal expansion) Pressure jump travels as shock wave at velocity of sound and bounces between walls Cavitation damage (pitting).
However, propagation of sound waves allows expansion of liquid Hg and release pressure: in ~ 30 μs expansion will reach adjacent volume (outside the 2 liter irradiated volume). Does this reduce problem?
Compare now SP and LP
SP: total pulse energy 23 kJ in 1 μs (<< 30 μs). No reduction
LP: only ~ 4 kJ in 30 μs (as 300 kJ pulse has 2 ms duration) so full energy distributed over much larger (2 orders magnitude) volume; moreover shock wave only due to the 4 kJ; it travels on top of continuously spreading pressure
Source and instrument characteristics need to be tailored to each other for optimal performance
Rencurel workshop *): Monte Carlo simulations on wide range of instruments, using pulse shaping and frame multiplication by using multiple choppers
Additional gains through modern neutron optics
Cold TOF: up to 100x IN5 at ILL under favourable conditions
Back scattering (among least favourable at LP source): still competitive with back scattering at SNS
SANS: considerably higher than any competitor (SP or CW) of equal time averaged flux; and for whole variety of SANS instruments now in use (focusing, magnetic, SESANS, ..)
Single crystal spectrometer: at least competitive
Protein Crystallography Station: shown to be feasible on LP source; will revolutionise applications of neutrons in protein crystallography
Reflectometers: outperforms ILL; competes very favourably with SNS
*) H. Schober et al, Nucl. Instr and Methods in Phys. Res., A 589 (2008) 34-46
Conclusion
Conclusion
Initial configuration is by far the best you can get for the price
Totally mature design: innovative combination of available technologies
Upgradeability warrants ESS will be with further relatively small investments best facility for next 40 years or so.
ESFRI Road Map (modeled after DoE 20-year facilities outlook) + strong desire of countries and European Commission to implement this
ESFRI Road Map (modeled after DoE 20-year facilities outlook) + strong desire of countries and European Commission to implement this
ESS and ILL 20/20 are the (only) neutron projects on this Road Map of European projects.
ESS is exactly as proposed by ESS Initiative: 5 MW LP upgradeable, same timeschedule (first neutrons 2017/2018). No need for new science review
UK Neutron Review
Science case unequivocal
Reviewing 1 MW upgrade of ISIS and new multi-MW European source :
‘next generation European Source’ is first priority.
No feasibility study into ISIS upgrade yet.
Three very serious site candidatures formally proposed by their governments and backed up with money
Scandinavia/Sweden: Lund
Scandinavia/Sweden: Lund
Spain/Basque Country: Bilbao
Hungary: Debrecen
Governments pledged each between 300 and 400 M€ for construction (including site premium); innovative schemes (either EIB’s Risk Sharing Financing Facility or - in Spain’s case - National Innovation Fund) to bridge mismatches between financing requirements and flow of contributions.