North Refineries Company was established in 1982 and it is the largest refining company among the Iraqi Ministry of Oil companies with design capacity of 402000 BPSD. NRC employed over 8,873 employees.
North Refineries Company was established in 1982 and it is the largest refining company among the Iraqi Ministry of Oil companies with design capacity of 402000 BPSD. NRC employed over 8,873 employees.
The company produces over 35 different type of product such as unleaded premium gasoline, illuminating kerosene, ATK, diesel, lube oil product, spindle oil, transformer oil, Asphalt, sulfur, LPG, RT … etc.
1- 310,000 BPSD Baiji Refining Capacity.
A- Salahuddin (1) Refinery with 70000 BPSD Refining Capacity.
B-North Refinery with 150000 BPSD Refining Capacity With 20000 BPSD small Two Units.
C- Salahuddin (2) Refinery with 70000 BPSD Refining Capacity.
2- New Isomerization Unit / 20,000 BPSD, in operation since July, 2011.
3- Lube Plant (two trains): 125000 Ton of different lube stocks per train.
4- Packaging and Loading Arms facilities.
5. Exterior Refineries:
5. Exterior Refineries:
A. Kirkuk Refinery with 30,000 BPSD Refining Capacity.
B. Siynia Refinery with 30,000 BPSD Refining Capacity.
Two units in operation and one unit under construction.
C. Kisik Refinery with 20,000 BPSD Refining Capacity.
One unit in operation and second under construction.
D. Qaiyarah Refinery with 34,000 BPSD Refining Capacity.
Needs to extend Crude Pipe line from the Strategic Line about 60 Km.
E. Hadithah Refinery with 16,000 BPSD Refining Capacity.
F. Aljazirah Refinery with 20,000 BPSD P28 Refining Capacity.
Planned to be re-engineering and reinstalling inside NRC.
6. Future Projects:
i. New Kirkuk Refinery with capacity of 150,000 BPSD.
ii. New FCC unit with capacity of 55,000 BPSD.
1983 was the year of operation.
1983 was the year of operation.
EPC has been done by CHIYODA.
The refinery operate 85% of its design capacity.
25,000 M3/Month of Naphtha is being injected back with the crude oil.
Because of the long operation life, sanctions, vandalism, and wars most of the units need rehabilitation.
New Kirkuk Refinery in Kirkuk City ( North of Iraq) 150,000 BPSD Refining Capacity FEED will be over by jun2012
New Kirkuk Refinery in Kirkuk City ( North of Iraq) 150,000 BPSD Refining Capacity FEED will be over by jun2012
Maissan Refinery in Maissan City ( South of Iraq)150,000 BPSD Refining Capacity.
Karbala Refinery in Karbala City ( South of Iraq) 200,000 BPSD Refining Capacity. Has been awarded to Italian company for investment.
Nasiriya Refinery in Nasiriya City ( South of Iraq) 300,000 BPSD Refining Capacity.