IDP PROCESS PLAN

JULY-PRE-PLANNING PHASE

ITEM. NO.

ACTIVITIES

NATURE OF THE MEETING

DATE

1.

Reviewal of the PMS framework plan

None

N/A

2.

Preparation of the IDP process plan

None

N/A

3.

Adoption of the IDP/Budget process and Framework plans

Special Council Meeting

08/2010

4.

Advertising of the framework plan

None




5.

Presentation of the project plans

Cluster meetings




6.

PMS reporting (2007/2008 reports)

Cluster meetings




7.

Preparations for the IDP launch

IDP/Budget steering committee




AUGUST-PLANNING PHASE

ITEM. NO.

ACTIVITIES

NATURE OF THE MEETING

DATE

1.

PMS reporting (Project progress)

Cluster meetings

2010

2.

Launch of the IDP

IDP rep. forum

20 August 2010

3.

Preparations for Community Based Planning

IDP/Budget steering committee

27 August 2010













SEPTEMBER-PLANNING PHASE

ITEM. NO.

ACTIVITIES

NATURE OF THE MEETING

DATE

1.

PMS reporting (Project progress)

Cluster meetings)

9th and 10th September 2010

2.

Reviewal of sector plans


None

01st to 30th September 2010

3.

Community Based Planning starts

Village and Ward meetings

01st to 30th September 2010

OCTOBER-ANALYSIS PHASE

ITEM. NO.

ACTIVITIES

NATURE OF THE MEETING

DATE

1.

PMS reporting (Project progress)

Cluster meetings

07th and 08th October 2010

2.

Preparations for the analysis phase

IDP steering committee

15/10/2010

3.


Considering reports from the wards (CBP)

IDP steering committee

15/10/2010

4.

Sector plan reports from the head of departments

IDP steering committee

15/10/2010

5.

Collecting of information from various sources by sectional heads.

None

01st to 31st October 2010

NOVEMBER-ANALYSIS PHASE

ITEM. NO.

ACTIVITIES

NATURE OF THE MEETING

DATE

1.

Presentation of the Situational Analysis to the steering committee

Steering Committee meeting


05 November 2010

2.

PMS reporting (Project progress)

Cluster meetings

11th and 12th November 2010

3.

Presentation of situational analysis

Cluster meetings

11th and 12th November 2010

4.

Reporting on Ward priorities

Cluster Meetings


11th and 12th November 2010

5.

Presenting the Situational Analysis and Ward priorities to Rep forum

IDP representative forum meeting

20 November 2010

DECEMBER-STRATEGIES PHASE

ITEM. NO.

ACTIVITIES

NATURE OF THE MEETING

DATE

1.

Receiving reports for the strategic session meeting from the section heads


None

04/12/2010

2.

Considering reports for strategic session

IDP/Budget steering committee

09/12/2010

JANUARY-STRATEGIES PHASE

ITEM. NO.

ACTIVITIES

NATURE OF THE MEETING

DATE

1.

PMS reporting (Project progress)


Cluster meetings

20th and 21st January 2011

2.

Final preparations for the Strategic session

IDP steering Committee Meeting

22/01/2011

3.

Reviewal of the strategies and objectives, setting up new objectives and strategies based on new priorities

Strategic session meeting

14th and 15th February 2011

FEBRUARY-STRATEGIES PHASE

ITEM. NO.

ACTIVITIES

NATURE OF THE MEETING

DATE

1.

PMS Reporting

Cluster meetings

17th and 18th February 2011

2.

Presentation of the strategies and objectives by cluster heads

Cluster Meetings

17th and 18th February 2011

3.

Determining projects based on the objectives and strategies

Cluster Meetings

17th and 18th February 2011

4.

Considering projects from other sector departments

IGR forum meetings


22nd to 26th February 2011

MARCH-PROJECTS PHASE

ITEM. NO.

ACTIVITIES

NATURE OF THE MEETING

DATE

1.

Presentation of the draft IDP and Budget to steering committee

IDP/Budget steering committee

07 March 2011

2.

PMS reporting (project progress)

Cluster meetings

10th and 11th of March 2011

3.

Presentation of the draft IDP to Rep. forum

IDP representative forum meeting

11 March 2011

4.

Presentation and approval of the draft IDP to and by council

Council Meeting

16 March 2011

5.

Advertising of the IDP, calling for public comments


None

17 March 2011

APRIL-APPROVAL PHASE

ITEM. NO.

ACTIVITIES

NATURE OF THE MEETING

DATE

1.

PMS reporting


Cluster meetings

07th and 08th April 2011

2.

Presentation of the IDP to the communities

IDP road shows

17 March to 08 April 2011

APRIL-APPROVAL PHASE

ITEM. NO.

ACTIVITIES

NATURE OF THE MEETING

DATE

1.

Looking at the comments from the roadshows


IDP Steering Committee Meeting

11/04/2011

2.

Presentation of the final draft IDP to steering committee


IDP Steering Committee meeting

18/04/2011

4.

Presentation of the final draft IDP to IGR

IGR

19/04/2011

5.

Presentation of the final draft IDP to rep forum

IDP representative forum

19/04/2011

6.

Approval of the final draft IDP by council

Council Meeting

20/04/2011

JUNE-APPROVAL PHASE

ITEM. NO.

ACTIVITIES

NATURE OF THE MEETING

DATE

1.

Printing of the IDP documents

None


N/A

2.

PMS reporting (Project progress)

Cluster meetings

09th and 10th June 2011

3.

Presentation of project plans

Cluster meetings

09th and 10th June 2011


4.

Presentation of the SDBIP and Municipal Scorecard to council

Council meeting

24 June 2011


2.3.2 BUDGET PROCESS PLAN

PROCESS

LEGISLATIVE REQUIREMENTS

RESPONSIBILITY

TIME FRAME

Implementation of the budget 2009/10 financial year
Start with the preparation of the next budget and review previous year’s budget checklist.


MFMA s53


Municipal Manager

Mayor


01 July 2010

31 July 2010



Mayor tables in council the schedule of key deadlines setting the time table for: preparing, tabling and approving the budget, reviewing the IDP and budget related policies and consultation processes at least 10 months before the start of the budget year.

Mayor establishes committees and consultation forums for the budget process



MFMA s21,22,23 and MSA s34, chapter 4

Mayor

30 August 2010


Council through the IDP review process determines strategic objectives for service delivery and development for next three –year budget including review of district, provincial and national government sector and strategic plans of Mbhashe Municipality.

National Treasury recommendation

Council

September -October 2010

Submit quarterly report to council on the implementation of the budget and financial affairs of the municipality

MFMA s 52 (d)



Mayor


10 October 2010



Council finalises tarrifs (rates and service charges) policies for the next financial year

MSA s 74,75

Council

November –December 2010

Assess the performance of the municipality in the first six months of the financial year

MFMA s 72

Municipal Manager

25 January 2011

Submit mid-year performance assessment report to council

MFMA s 54 (1) (f)

Mayor

31 January 2011

Review proposed national and provincial allocations and projects for the next three years information which will be made available

MFMA s36

Municipal Manager

25 January 2011

Table the adjustments budget for 2009/10 if necessary

MFMA 72 (3)

Mayor

February 2011

Annual budget tabled at council at least 90 days before the start of the budget year.

MFMA 16 (2)

Mayor

30 April 2011

Public hearings on the budget and council debate.
Council consider views of the local community, National Treasury, provincial Treasury and other organs of the state.
Mayor to be provided with an opportunity to respond to submissions during consultation and table amendments for council consideration.

Council to consider approval of budget and plans at least 30 days before start of budget year.




MSA Chapter 4 as amended
MFMA 23(1)

MSA Chapter 4 as amended

MFMA 24(1)


Mayor

Council


Mayor
Council

May 2011

May 2011


May 2011
30 May 2011

Consider approval of annual budget 2010/11 by resolution, setting taxes and tarrifs.

Approving changes to IDP and budget related policies.

Approving measurable performance objectives for revenue by source and expenditure by vote before start of budget year


MFMA s 16,24,26,53

Council

June 2011

Submit Service delivery implementation plan (SDBIP) 2010/11 within 14 days after approval of the budget

MFMA 69(3)

Municipal Manager

14 June 2011

Approval of Service delivery implementation plan (SDBIP) 2010/11 within 28 days after the approval of the budget and ensure that annual performance contracts are included in accordance with s 57(2) of the MSA.
Ensure that the annual performance agreements are linked to the measurable performance objectives approved with the budget and SDBIP.
The mayor submits the approved SDBIP and performance agreements to council, MEC for Local Government and makes public within 14 days after approval.

MFMA s 53

MSA s38-45, 57(2)




Mayor

28 June 2011


CHAPTER 2: SITUATIONAL ANALYSIS
2.1 MBHASHE DEMOGRAPHIC PROFILE
2.1.1 MBHASHE IN CONTEXT
Mbhashe municipality is situated in the south eastern part of the Eastern Cape Province, and is bound by the Qhora River in the south to Mncwasa River in the north along the Indian Ocean. The municipality borders the following municipalities:

King Sabata Dalindyebo (in the eastern part)

Ngcobo (to the western part)

Mnquma (to the South)



NtsikaYethu (in the South-Western part)
Mbhashe has earned the name from the beautiful river called Mbhashe which flows from the banks of Ngcobo flowing through Dutywa, Gatyana (Willowvale) and Xhora (Elliotdale). Mbhashe is comprised of the three towns of Dutywa, Gatyana and Xhora and numerous rural settlements. The area also boasts the head offices of the AmaXhosa Kingdom at Nqadu Great Place.
Mbhashe is 3030.47 km² in area and consists of 31 wards and 61 Councillors. The vision of the Municipality is a “vibrant institution able to provide quality and accessible services to all its communities in a socio economic manner, with the aim of benefitting her people”. Four clusters of key development priorities are identified i.e. LED and Environment, Social Needs, Infrastructure and Institutional and Finance clusters which were aligned to five local governments’ key performance areas.
The new demarcation of municipal boundaries was conducted in preparation for the Local government elections. The Mbhashe Local Municipality will be composed of 31 wards which include areas from Intsika Yethu Municipality and Mnquma. The areas which form part of Mbhashe are Keti, Sikobeni, Ziwundane, Mqonci, and Gwadana Tribal.
Mbhashe is predominantly rural, with high levels of unemployment, poverty and dependency. The dependency ratio is set to increase if employment opportunities are not created for the large and youthful population. Mbhashe’s location on the Wild Coast provides the key for potential economic growth as the area is said to be one of the most sought after coastal tourism destinations in the Eastern Cape. The municipality has developed its own official LED strategy and is aligned the Amathole District Strategy and is investigating means to exploit the Wild Coast’s potential, and will make use of the Amathole District’s plans and focus on the development and expansion of Agriculture, forestry, mining and tourism. The road networks are severely under-maintained with few roads that are tarred, which adds to the economic challenges experienced by the local population as many rural areas and basic services, such as schools, are inaccessible.
Yüklə 2,37 Mb.

Dostları ilə paylaş:
1   2   3   4   5   6   7   8   9   ...   21




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin