So far till October 2010 the department has maintained (blading and compaction) 24km of access roads and fixes potholes in Dutywa, Willowvale and Elliotdale on need basis. There is an estimated requirement of maintaining of 833km of gravel roads and 72km of tar roads but the available fund is not enough to address the issue. The department has also developed Mantainance plan as from 01 February 2011 which is presented below:
|
|
|
2.6.8.2 ROADS MAINTENANCE
|
|
|
DRAFT MAINTENANCE PLAN 2011
|
|
|
|
Total Km
|
891.60
|
|
|
Budget Needed
|
R 4,458,000.00
|
|
|
|
|
|
Ward
|
Road Name
|
Activity Description
|
Length Km
|
26
|
Qinqana to Gongco
|
Wet Grading and Compaction
|
5.50
|
|
Shimrha to Botwe
|
Wet Grading and Compaction
|
5.00
|
|
Mantyi to Ngqatyane
|
Wet Grading and Compaction
|
6.00
|
|
Madwaleni to Khosani
|
Wet Grading and Compaction
|
6.00
|
|
Mphafeni to Manaleni
|
Wet Grading and Compaction
|
3.50
|
|
|
Sub-total
|
26.00
|
24
|
Qhingqala
|
Wet Grading and Compaction
|
6.00
|
|
Shixini
|
Wet Grading and Compaction
|
2.00
|
|
Phathilizwe
|
Wet Grading and Compaction
|
8.00
|
|
Xonyeni
|
Wet Grading and Compaction
|
6.00
|
|
Mhlabulungile
|
Wet Grading and Compaction
|
5.00
|
|
Upper Gwadu
|
Wet Grading and Compaction
|
3.50
|
|
Nombembe
|
Wet Grading and Compaction
|
2.00
|
|
Lubomvini
|
Wet Grading and Compaction
|
8.00
|
|
Jojweni
|
Wet Grading and Compaction
|
6.00
|
|
Nkelekete
|
Wet Grading and Compaction
|
8.00
|
|
Ntilini
|
Wet Grading and Compaction
|
8.10
|
|
|
Sub-total
|
62.60
|
23
|
Sponono
|
Wet Grading and Compaction
|
2.50
|
|
Nebelele
|
Wet Grading and Compaction
|
5.00
|
|
Rhafani
|
Wet Grading and Compaction
|
2.00
|
|
Bokweni
|
Wet Grading and Compaction
|
2.00
|
|
Mhlahlane
|
Wet Grading and Compaction
|
3.00
|
|
Old Qwaninga
|
Wet Grading and Compaction
|
3.00
|
|
Manxiwa
|
Wet Grading and Compaction
|
2.00
|
|
Mntonga to Mantlaneni
|
Wet Grading and Compaction
|
6.00
|
|
Ngxutyana JSS
|
Wet Grading and Compaction
|
2.00
|
|
Msintsini to Ngcizela
|
Wet Grading and Compaction
|
3.00
|
|
Nohantam line
|
Wet Grading and Compaction
|
2.50
|
|
Jotela
|
Wet Grading and Compaction
|
5.00
|
|
Folokwe
|
Wet Grading and Compaction
|
5.00
|
|
Zwelinzima JSS
|
Wet Grading and Compaction
|
2.00
|
|
|
Sub-total
|
45.00
|
22
|
KwaMacinga to Maxixibeni
|
Wet Grading and Compaction
|
5.00
|
|
Nocwane Store to Project
|
Wet Grading and Compaction
|
2.50
|
|
KwaVenge to Nkatha
|
Wet Grading and Compaction
|
11.00
|
|
|
Sub-total
|
18.50
|
21
|
All covered on Voting Station roads.
|
|
|
20
|
Khangelani Cafe to Bhula
|
Wet Grading and Compaction
|
15.00
|
|
Phokoloshe to Gobizembe
|
Wet Grading and Compaction
|
20.00
|
|
Dingata to Mbanyana
|
Wet Grading and Compaction
|
15.00
|
|
Nkanya to Mabholobela
|
Wet Grading and Compaction
|
15.00
|
|
Makhamese to Lalini
|
Wet Grading and Compaction
|
15.00
|
|
Haven to Geya
|
Wet Grading and Compaction
|
15.00
|
|
Geya to Xeni
|
Wet Grading and Compaction
|
5.00
|
|
Hobeni to Thembani
|
Wet Grading and Compaction
|
4.00
|
|
Hobeni to Ngxabane
|
Wet Grading and Compaction
|
10.00
|
|
Rebeshani to Mangqosini
|
Wet Grading and Compaction
|
5.00
|
|
Hobeni to Mdeni
|
Wet Grading and Compaction
|
7.00
|
|
Mdeni to Mncwana
|
Wet Grading and Compaction
|
5.00
|
|
Makhameso to Mbelu
|
Wet Grading and Compaction
|
6.00
|
|
Khangelani to Mafusini
|
Wet Grading and Compaction
|
6.00
|
|
Cwebe Road to Mampondweni
|
Wet Grading and Compaction
|
3.00
|
|
|
Sub-total
|
146.00
|
19
|
Mtonjeni to Nguberhamba SPS
|
Wet Grading and Compaction
|
20.00
|
|
Mpame road to KumkwanaSPS
|
Wet Grading and Compaction
|
5.00
|
|
Zitulele road to Lubanzi
|
Wet Grading and Compaction
|
7.00
|
|
|
Sub-total
|
32.00
|
18
|
|
Wet Grading and Compaction
|
15.00
|
|
Thelekhulu to Mncwasa river
|
Wet Grading and Compaction
|
5.00
|
|
Bafazi to Nditya
|
Wet Grading and Compaction
|
2.00
|
|
|
Sub-total
|
22.00
|
17
|
Tafalehashe to Delingubo
|
Wet Grading and Compaction
|
5.20
|
|
Ntlonyane to Mtshekelweni
|
Wet Grading and Compaction
|
5.00
|
|
Zembe to Bufumba
|
Wet Grading and Compaction
|
5.20
|
|
Kulohesha to Sidabekweni
|
Wet Grading and Compaction
|
4.80
|
|
Mqhele to Mrhabe
|
Wet Grading and Compaction
|
4.20
|
|
Mqhele Jss
|
Wet Grading and Compaction
|
0.50
|
|
Vulindaba
|
Wet Grading and Compaction
|
0.50
|
|
Mpakama
|
Wet Grading and Compaction
|
0.30
|
|
|
Sub-total
|
25.70
|
16
|
Bovane Clinic to Bumbane
|
Wet Grading and Compaction
|
3.00
|
|
Mount Pleasant to Madwaleni
|
Wet Grading and Compaction
|
3.00
|
|
Shelton to Pokoloshe
|
Wet Grading and Compaction
|
3.00
|
|
Shelton to Gwebizembe
|
Wet Grading and Compaction
|
4.00
|
|
Gwebindlala JSS to Mwana
|
Wet Grading and Compaction
|
1.50
|
|
|
Sub-total
|
14.50
|
15
|
Nkentshu to Tandiwe
|
Wet Grading and Compaction
|
7.00
|
|
Dabane to Lalini
|
Wet Grading and Compaction
|
2.20
|
|
Nqabayi to Sarhili
|
Wet Grading and Compaction
|
5.00
|
|
|
Sub-total
|
14.20
|
14
|
Bunga to Dalukhanyo
|
Wet Grading and Compaction
|
7.00
|
|
Ndude to Mbashe
|
Wet Grading and Compaction
|
2.00
|
|
Ndude to Lukhozana
|
Wet Grading and Compaction
|
2.00
|
|
Lukhozana to Upper Mbangcolo
|
Wet Grading and Compaction
|
3.00
|
|
Mtshazi SPS to Mndundu JSS
|
Wet Grading and Compaction
|
12.00
|
|
|
Sub-total
|
26.00
|
13
|
Majavu to Melitafa
|
Wet Grading and Compaction
|
20.00
|
|
Kasa to Riverview
|
Wet Grading and Compaction
|
20.00
|
|
Fameni to Cuntsula
|
Wet Grading and Compaction
|
15.00
|
|
Elliotdale to Technical
|
Wet Grading and Compaction
|
2.00
|
|
Majavu to Ncihana
|
Wet Grading and Compaction
|
3.00
|
|
Elliotdale to Ncihana JSS
|
Wet Grading and Compaction
|
6.00
|
|
Gwenteshe Junction to Makhamisa
|
Wet Grading and Compaction
|
5.00
|
|
Makhamisa shop to Mhlanga
|
Wet Grading and Compaction
|
10.00
|
|
Bhengu to Velelo
|
Wet Grading and Compaction
|
5.00
|
|
Magiqweni to Fameni Project
|
Wet Grading and Compaction
|
2.50
|
|
Mgwede to Phesheya Komnyama
|
Wet Grading and Compaction
|
6.00
|
|
|
Sub-total
|
94.50
|
12
|
Gxaka Gxaka
|
Wet Grading and Compaction
|
5.00
|
|
Fort Malan JSS
|
Wet Grading and Compaction
|
5.00
|
|
|
Sub-total
|
10.00
|
11
|
Ncedana to Mbethe
|
Wet Grading and Compaction
|
5.00
|
|
Pagasini
|
Wet Grading and Compaction
|
5.00
|
|
Dadamba to Matanzima
|
Wet Grading and Compaction
|
6.00
|
|
Dadamba to Gwabe
|
Wet Grading and Compaction
|
6.00
|
|
|
Sub-total
|
22.00
|
10
|
Bomela to Mzimkhulu
|
Wet Grading and Compaction
|
5.00
|
|
Mbukuqe to taleni JSS
|
Wet Grading and Compaction
|
5.00
|
|
Ntlabane to Kulokhala
|
Wet Grading and Compaction
|
5.00
|
|
Ntlabane Junction to Ntlabane
|
Wet Grading and Compaction
|
5.00
|
|
|
Sub-total
|
20.00
|
9
|
Murumuru to Mabheleni
|
Wet Grading and Compaction
|
4.00
|
|
|
Sub-total
|
4.00
|
8
|
Mpini to Enweleni
|
Wet Grading and Compaction
|
4.00
|
|
Chachazele to Vulingcobo
|
Wet Grading and Compaction
|
1.00
|
|
Maqundeni to Chaphaza
|
Wet Grading and Compaction
|
6.00
|
|
Stiyana to Khanya
|
Wet Grading and Compaction
|
3.00
|
|
Stishini to Kreqweni
|
Wet Grading and Compaction
|
11.00
|
|
Qombe to Gqubeni
|
Wet Grading and Compaction
|
4.00
|
|
Cerhu to Sibane
|
Wet Grading and Compaction
|
11.00
|
|
|
Sub-total
|
40.00
|
7
|
Mazwayi to Mabheleni
|
Wet Grading and Compaction
|
5.00
|
|
Komkhulu to Ezithenjini
|
Wet Grading and Compaction
|
6.00
|
|
Esihlabeni to Gungululu
|
Wet Grading and Compaction
|
6.70
|
|
|
Sub-total
|
17.70
|
6
|
Mhuku to Njemane
|
Wet Grading and Compaction
|
8.00
|
|
Thembalethu to Bekizulu
|
Wet Grading and Compaction
|
5.00
|
|
Lota store to Mlondzi
|
Wet Grading and Compaction
|
5.00
|
|
Mlondzi to Masango
|
Wet Grading and Compaction
|
2.00
|
|
N2 to Nkawukazi
|
Wet Grading and Compaction
|
3.00
|
|
Nkawukazi to Mantshilibeni
|
Wet Grading and Compaction
|
3.00
|
|
Nywara to Mhuku
|
Wet Grading and Compaction
|
5.00
|
|
Harmanas to Makinana
|
Wet Grading and Compaction
|
2.00
|
|
Mlonzi to Zimlindile SPS
|
Wet Grading and Compaction
|
2.00
|
|
Singeni to Makhobokeni
|
Wet Grading and Compaction
|
5.00
|
|
Ngqokweni to Esingeni
|
Wet Grading and Compaction
|
3.00
|
|
Nqabane store to Mabheleni
|
Wet Grading and Compaction
|
3.00
|
|
|
Sub-total
|
46.00
|
5
|
Mazizini
|
Wet Grading and Compaction
|
4.00
|
|
Vinindwa
|
Wet Grading and Compaction
|
4.00
|
|
Vonqo
|
Wet Grading and Compaction
|
5.00
|
|
Bolotwa
|
Wet Grading and Compaction
|
3.50
|
|
Nyakatha
|
Wet Grading and Compaction
|
4.00
|
|
Mazizini to Vinindwa
|
Wet Grading and Compaction
|
5.00
|
|
Nyakatha to Qolweni
|
Wet Grading and Compaction
|
4.50
|
|
(DR 08279) Sihlabeni to Bolotwa
|
Wet Grading and Compaction
|
5.00
|
|
Mbanga
|
Wet Grading and Compaction
|
4.50
|
|
Bangweni
|
Wet Grading and Compaction
|
2.50
|
|
|
Sub-total
|
42.00
|
4
|
Mbewuleni
|
Wet Grading and Compaction
|
3.00
|
|
Timane Junction to Gaxa JSS
|
Wet Grading and Compaction
|
9.80
|
|
Gxara to Mangwevini
|
Wet Grading and Compaction
|
5.00
|
|
Sinqumeni to Nyakatha JSS
|
Wet Grading and Compaction
|
5.00
|
|
Zithenjini Junction to Munyu JSS
|
Wet Grading and Compaction
|
5.00
|
|
|
Sub-total
|
27.80
|
3
|
Qhorha
|
Wet Grading and Compaction
|
5.00
|
|
Mahliwane
|
Wet Grading and Compaction
|
2.00
|
|
Gwadana Mission to Ndenga
|
Wet Grading and Compaction
|
4.50
|
|
Gwadana Tribal Authority
|
Wet Grading and Compaction
|
8.00
|
|
Gwadana Mission to Manya
|
Wet Grading and Compaction
|
3.50
|
|
Mpepheni to Qelane
|
Wet Grading and Compaction
|
4.00
|
|
Mpepheni to Tyholomi
|
Wet Grading and Compaction
|
6.00
|
|
Lusizini to Zimpuku
|
Wet Grading and Compaction
|
3.00
|
|
|
Sub-total
|
36.00
|
2
|
Xeni to upper Colosa
|
Wet Grading and Compaction
|
20.00
|
|
|
Sub-total
|
20.00
|
1
|
Doti Access Road
|
Wet Grading and Compaction
|
7.00
|
|
Govan Mbeki to Doti
|
Wet Grading and Compaction
|
3.00
|
|
Dutywa to Govan Mbeki
|
Wet Grading and Compaction
|
5.00
|
|
Govan Mbeki to Phola Park
|
Wet Grading and Compaction
|
2.00
|
|
Govan Mbeki Township streets
|
Wet Grading and Compaction
|
15.00
|
|
Whack Street
|
Wet Grading and Compaction
|
2.40
|
|
Maduna Street
|
Wet Grading and Compaction
|
2.00
|
|
Streetfield
|
Wet Grading and Compaction
|
3.00
|
|
Stanford street
|
Wet Grading and Compaction
|
3.00
|
|
CBD Roads
|
Wet Grading and Compaction
|
19.10
|
|
Dutywa to New Rest
|
Wet Grading and Compaction
|
2.10
|
|
Dutywa to GPO
|
Wet Grading and Compaction
|
1.50
|
|
Extension 8 Access Roads
|
Wet Grading and Compaction
|
14.00
|
|
|
Sub-total
|
79.10
|
|
|
Total
|
891.60
|