Meski Çevre yönetim plani hazirlik dokümani



Yüklə 469,42 Kb.
səhifə2/7
tarix03.08.2018
ölçüsü469,42 Kb.
#67207
1   2   3   4   5   6   7

1.2METHOD AND SCOPE


MESKİ had a feasibility study and a project done by Mavi Mühendislik firm in 2005 for said project to be included in the Municipal Services Project (Mavi Müh., 2005). MESKİ, being included in the financial support process with this study, has first invited tenders for a Consulting Service to execute construction of connection of reservoir, rising center and connection lines between reservoirs, which makes part of the Mersin Water Supply Rehabilitation Project and which will provide distribution of water at east-west direction of the city. In order to perform this service, a contract was signed between MESKİ and Temelsu Uluslararası Mühendislik Hizmetleri A.Ş. in 13.02.2007 for the work of 'Examination, Preparation of Tender Documents and Consulting Services for the Implementation Projects of Reservoirs, Connection Lines Between Reservoirs and Rising Centers (Contract No. MES C2)’. Under the scope of Consulting Services, first the project data of 2005 will be examined and updated. In parallel, these projects will be made a final project, tender documents will be prepared, the tender process will be supported and construction supervision will be provided.
Under the scope of the abovementioned implementation project, an Environmental Management Plan (EMP) must be established to examine and assess its Environmental Impacts during construction and operation processes and to minimize such impacts. For this purpose, MESKİ has signed a contract in 05.04.2007 to have Private Consulting Services with Assoc. Prof. Erdem Görgün, executive director of io Environmental Solutions Research and Development Company.
Within the content of this Environmental Management Plan, measures to be taken against the specified likely impacts and monitoring parameters of these measures have been determined. Organizations and institutions responsible in implementation process of this plan was defined and their obligations were specified. Additionally, sufficiency of these organizations in meeting their obligations were examined and the actions they should take to repair their defects were defined.
Environmental impacts on people living in regions where the project was implemented were examined and a "Public Awareness Meeting" was held on April 30, 2007. A work programme was established in accordance with all these assessments and an Environmental Management Plan was prepared in which the Plan stages were detailed.
Works performed under this scope may be listed as follows.


  1. Category B Environmental Assessment under "Environmental Framework for Municipal Services Project

  2. Preparation of the "Environmental Management Plan", which is the main document for Category B Environmental Assessment under OP 4.01 document.

  3. Public Participation Meetings


2DESCRIPTIONS OF THE REHABILITATION PROJECT

2.1BACKGROUND OF THE PROJECT


After establishment of Mersin Greater Municipality with the Decree of Force of Law no 504 dated 09.09.1993, General Directorate of Mersin Water and Sewerage Administration (MESKİ) was established with the decision no. 95/6750 dated 04.05.1995 of the Board of Ministers to provide Water and Sewerage services of the Mersin Greater Municipality and for this purpose, to establish all plants needed, to take over all existing ones and to operate them centrally. MESKİ (Mersin Greater Municipality, General Directorate of Water and Sewerage Administration) is responsible for provision of services for water, sewerage system, wastewater treatment and stormwater drainage to residential units in the service area of Mersin Greater Municipality. Last project about water supply system of the Town Center was made in 1994. Particularly because of rapid population growth since this date and enlargement of service area of the Mersin Greater Municipality, existing water supply system became insufficient. Thus, MESKİ had a project study done by Mavi Mühendislik firm in 2005 for extension of main supply system consisting of main supply lines, reservoirs and rising centers. With this study, MESKİ signed a Sub Credit Agreement of 25,056,918 Euros in 08.02.2006.
169 km section of existing 1,250 km water supply network has been replaced by the operator firm and MESKI demands replacement of remaining part by using HDPE type pipes under this credit. With the credit support, 25.056.918 Euros of the cost of abovementioned Project of Water Supply Network Rehabilitation and Construction of Reservoir and the Connection Lines Between Reservoirs (27,340,458 Euros) is provided.

2.2PROJECT CONTENT


In the existing water supply system of Mersin, there are 6 water reservoirs and 3 pumping stations. The network consists ACP (Asbestos Cement Pipe), Cast Iron, PE and PVC pipes with various diameters. There are 6 pressure zones in the system. In order to reduce the loss-unaccounted for water rate about 65% in Mersin, an inspection was made and in particular ACP (Asbestos Cement Pipe) and Cast Iron pipes were specified to cause physical losses. With the rehabilitation project, priority was given to replacement of these pipes. (MESKİ, 2006)
Target of this project is to provide sufficient operation pressure by reorganizing the pressure zones, to measure the water distribution amounts with fixed flowmeters by forming local measurement areas, to minimize physical and illegal losses in the system and both to reduce the loss rate and to ensure healthful potable water transmission by replacing the asbestos and cast iron pipes at the end of their life with HDPE (High Density Polyethylene) pipes. Precautions regarding to disposal of ACP are explained in further sections. Moreover, in order to stabilize water coming with the 2nd Transmission line, the project also consists new reservoirs, rising centers and rising mains. Also personnel trainings are made for continuation of operational productivity. (MESKİ, 2006)
General target of the water supply rehabilitation project is to increase MESKI's technical and financial service level in a sustainable level. Target of this contract is to ensure supply of water to consumers with appropriate pressure and sufficient quantity, with the physical investment under the project, with most appropriate investment cost.
"Water Supply Structures Rehabilitation Project", with the general layout in town shown in Figure 1, is divided into two main parts:


  1. Improvement of the existing network

  2. Construction of new Reservoirs and Rising Centers

Works to be carried out in this scope may be summarized as follows:



2.2.1Improvement of the existing network


Data of the network to be rehabilitated with the existing network given in Table 2 .1 include statements made by Mavi Mühendislik firm in 2005. In the assessments made here it was stated that project assumptions could be changed with the loss-unaccounted for water control to be made at site. Priority will be given to control and rehabilitation of main and basic pipes in implementation of this project. MESKI, Bank of Provinces and State Hydraulic Works (DSI) archives were scanned and surveys were made at site with MESKI's water network chief. As a result of the studies carried out, it was decided to keep PVC and PE pipes with  100 mm and above diameter laid in 1994 and later. (Mavi Müh., 2005)

Table 2.1 Existing Water Supply Network Lines and Suggestions (Mavi Müh. 2005)


Diameter

1.Zone

2.Zone

3.Zone

4.Zone

5.Zone

6.Zone

7.Zone

8.Zone

Total

Ø 110 PE

27,153

308,095

82,099

29,556

15,338

15,825

2,003

6,813

486,882

Ø 140 PE

11,312

28,159

8,032

5,488

3,067

3,514

112

515

60,199

Ø 160 PE

17,043

44,884

19,546

1,934

1,950

4,046

0

675

90,078

Ø 200 PE

236

0

0

0

0

0

0

0

236

Ø 225 PE

13,539

19,271

5,158

2,012

2,250

4,617

631

816

48,294

Ø 280 PE

4,659

14,148

5,630

6,956

494

1,293

0

677

33,857

Ø 355 PE

11,261

7,350

935

1,003

2,735

836

16

372

24,508

Ø 350 PE

4,387

11,361

1,617

1,772

0

490

0

610

20,237

Ø 400FRP

7,283

4,615

0

840

512

3,462

832

0

17,544

Ø 450 FRP

0

327

0

0

0

0

0

0

327

Ø 500 FRP

9,142

6,891

6,575

3,260

1,245

507

535

520

28,675

Ø 600 FRP

2,853

2,339

2,946

1,974

1,839

3,359

0

1,080

16,390

Ø 700 FRP

2,440

35

1,558

998

0

0

0

0

5,031

Ø 800 FRP

1,145

8,120

0

0

0

573

0

0

9,838

Ø 900 FRP

0

890

0

940

0

1,164

0

0

2,994

Ø 1000 FRP

0

876

2,402

0

0

0

0

0

3,278

Ø 1200 FRP

0

5,543

0

0

0

986

0

0

6,529

WILL BE REHABİLİTATED

112,453

462,904

136,498

56,733

29,430

40,672

4,129

12,078

854,897

WILL NOT BE CHANGED

113,192

211,746

22,285

50,443

17,437

0

0

0

415,103

WILL BE NEEDED IN THE FOLLOWING YEARS

43,898

120,411

20,173

71,202

52,625

51,894

134,569

17,117

511,889

GRAND TOTAL

269,543

795,061

178,956

178,378

99,492

92,566

138,698

29,195

1,781,889

2.2.2Construction of New Reservoirs and Rising Centers


In the feasibility study of 2005, Reservoir Volume requirements were specified using data calculation methods of the Bank of Provinces, and additional reservoir requirements were determined accordingly. Based on the Project Consultancy in March 2007, designs of 2005 were subjected to a preliminary check, according to the agreement made with Temelsu Mühendislik. Accordingly, calculation methods of the Bank of Provinces and DSİ were compared and taking the fire flows into consideration in addition to the 2005 calculations, optimum values for reservoir volume requirements were obtained. The plants, which are proposed in accordance with these reservoir volume figures are given in Table 2 .2 and Table 2 .3. Monitoring and supervision plans for proposed additional reservoirs, are explained in further sections.

Table 2.2 Proposed Additional Reservoirs (Temelsu 2007)



Proposed Additional Reservoirs

Reservoir Name

Volume (m3)

Max. Depth (m)

Min. Depth (m)




DY2

20.000

71.00

65.50




DY2A

15.000

85.25

80.25




DY3

10.000

108.40

103.40




DY4

5.000

149.50

144.50




DY6

5.000

129.50

124.50




DY7

4.000

222.00

217.50




DY8

4.000

183.50

179.00




DY9 (2. Stage)

1500

230.00

226.00




Total Proposed Addition Reservoir Volume (m3)

63.000 (1. Stage)

64.500 (2. Stage)

* DY: Proposed New Reservoir

Table 2.3 Proposed Additional Rising Centers (Temelsu 2007)



Proposed Rising Centers

Rising Center Name

Pump Feeded by (Reservoir)

Pumping to

Stage

Number and Properties of Pumps

TMY1

D1

D2-DY2 Reservoirs and TMY2 Rising Center

1. Stage


Q= 288 l/s

Hm= 40.00 m

6 adet


TMY2

DY2A

D6-DY6

1. Stage

Q= 138 l/s

Hm= 58.00 m

3 adet


P2 Pumping Station

D3-DY3

D4-DY4

1. Stage

Q= 81 l/s

Hm= 56.00 m

3 adet


TMY4

D2-DY2

DY2A

1. Stage

Q= 250 l/s

Hm= 31.00 m

5 adet


TMY5

D6-DY6

DY8

1. Stage

Q= 36 l/s

Hm= 73.00 m

3 adet


TMY6

D5

DY7

1. Stage

Q= 22.5 l/s

Hm= 105.00 m

3 adet


TMY7

DY8

DY9

2. Stage

Q= 15 l/s

Hm= 72.00 m



  1. adet

* TMY: Proposed Rising Center

Table 2.4 Proposed Additional Connections Between Reservoirs (Temelsu 2007)

Proposed Additional Connections Between Reservoirs

Between -------- / -------- Connection Pipe

Pipe Length (m)

Pipe Diameter (mm)

Pipe Type




D1 / D2-DY2

3419.00

1100

FRP




D2-DY2 / DY2A

3865.00

900

FRP




DY2A / D6-DY6

1546.00

500

FRP




D6-DY6 / DY8

1512.00

280

HDPE




DY8 / DY9 (2. Stage)

1000.00

125

HDPE




D3-DY3 / D4-DY4

2969.00

400

FRP




D4-DY4 / D7-DY7

2328.00

225

HDPE




FRP: Fiber-glass Reinforced Plastic Pipe

HDPE: High Density Polyethylene



Figure 2.1 Proposed Water Distribution System (Temelsu 2007)




Figure 2.2 Existing P1 Pumping Station and TMY1 Rising Center Location



Figure 2.3 DY3 Reservoir Location (Through D3 Reservoir)

Yüklə 469,42 Kb.

Dostları ilə paylaş:
1   2   3   4   5   6   7




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin