3.3MONITORING PLAN


In this section of the report, in order to ensure conformity of activities, which will be carried out in planning/design, construction and operation stages of the project, with principles and procedures stated in the national environmental legislations, said stages were established and the following "Monitoring Plan" was created.
Table 3.10 Monitoring Plan During Construction

Stage

What parameters will be monitored?

Where will the parameters be monitored?

How will the parameters be monitored?/ Monitoring equipment

When will the parameters be monitored?/ Measuring frequency or continuous measurement

Responsible organization/ institution

Construction

Fate of Excavation waste

Construction routes/temporary and final storage areas

Visual

Dailly

Contractor and Supervisor

Used pipe waste

Construction routes/temporary and final storage areas

Visual

Dailly


Contractor and Supervisor

Historic, cultural and archeological assets

Construction route

Visual


When cultural assets are found

Contractor and Supervisor

Dust/air pollution

Construction site and vehicles carrying material

Visual


During work

Contractor and Supervisor

Noise (working machines and carrying vehicles)

Working machines working in the construction site

Sound ranging instrument will be used during work hours.

Monthly or when people living around complaints.

Contractor and Supervisor

Exhaust fumes

Roads and construction zones.

By checking Exhaust Measurement Licenses of vehicles.

When vehicles start operation.

Contractor and Supervisor

Excavation

In the construction site

By checking the permissions received

When vehicles start operation.

Contractor and Supervisor

Public safety

Construction route

Visual and standart control

Continuous

Contractor and Supervisor

Disposal of Asbestos Cement Pipes.

Temporary and final landfill areas of pipes.

Visual

When ACP’s are replaced with new pipes.

Contractor and Supervisor

Construction site restoration

In the construction site

Visual

At the end of the construction site

Contractor and Supervisor



Table 3.11 Monitoring Plan During Operation

Stage

What parameters will be monitored?

Where will the parameters be monitored?

How will the parameters be monitored?/ Monitoring equipment

When will the parameters be monitored?/ Measuring frequency or continuous measurement

Responsible organization/ institution

Operation

Disasters and accidents

Valve rooms, pipes, reservoirs and water storages

Visual and with practice

On complaint and periodically

MESKİ

Safety of water structures

Monitoring the water supply structures with the Scada system

Visual, SCADA System and standart control

Dailly

MESKİ

Monitoring Water Quality

Monitoring the water supply structures with the Scada system; particularly disinfection of water

SCADA System, random measurements and analysises and standart control

Dailly

MESKİ

Continuity of Disinfection

Disinfection with efficient chlorination is applied in Berdan Water Treatment Plant. In addition to chlorination, establishment of an Ozonning Unit is planned by MESKI. An efficient monitoring will be made against mixing to occur in the network, by analysis carried out continuously from various points.

SCADA System, random measurements and analysis and standart control

Dailly

MESKİ

Safety of disinfectant tanks

In disinfectiant tank room

Air quality equipment

Sürekli

MESKİ



Yüklə 469,42 Kb.

Dostları ilə paylaş:
1   2   3   4   5   6   7




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin