Monthly Operational Summary of Bank and ida proposed Projects


(R) SL: Western Area Power Generation Project



Yüklə 1,07 Mb.
səhifə153/621
tarix07.01.2022
ölçüsü1,07 Mb.
#90140
1   ...   149   150   151   152   153   154   155   156   ...   621
(R) SL: Western Area Power Generation Project: In May 2014 the Government of Sierra Leone requested IDA for a guarantee for the proposed Western Area Power Generation Project (WAPGP) to be developed as an independent power producer selling to electricity the Electricity Distribution and Supply Authority (EDSA).

WAPGP is part of the Government’s plan for private sector participation in the generation subsector to meet electricity demand. The Project is proposed as a 128 MW Heavy Fuel Oil (HFO) fired power plant to be located on an existing industrial site about 4 km outside Freetown. The Project is to be constructed in phases over three to four years, of which the first phase is 50MW. Approval completed on 14 July 2016. Environmental Assessment Category B. Project: P153805. US$ 40.0 (GUID). Consulting services to be determined. Implementing agency(ies) to be determined.




Yüklə 1,07 Mb.

Dostları ilə paylaş:
1   ...   149   150   151   152   153   154   155   156   ...   621




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2025
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin