|
Check that the construction complies with the distribution construction standards and applicable design drawings.
|
|
Check the switchgear to ensure the switch is in the OFF position. N/A
|
|
Check the equipment mimic diagram to confirm the earth switch is in the ON position. N/A
|
|
Ensure that the interlock is disengaged to access the cable/compartment for test purposes
|
|
Confirm that the cables are de-energised (with an approved testing device) before proceeding further.
|
|
Ensure that the earthing system is complete, undamaged and bonded to earth points.
|
|
Wherever possible, check that there is no physical damage to the cable or equipment.
|
|
Check that the cable is clearly marked with each phase colour and labelled (if applicable).
|
|
Ensure the surge arresters are disconnected from the cable terminations (if applicable).
|
|