Final PBS-ESAP2 Midterm Review Report sent to GoE July17
Table 2: ESAP2 Coverage and SAIPs Progress in Summary – On 1
st
and 2
nd
cohort implementation variations, refer to annex 3
Region Woredas (all) Woredas (ESAP2) SAIPs (#) Salient characteristics on implementation status Addis Ababa
116
18
9
1 woreda completed service improvement action plan and is
monitoring implementation; 9 are applying SA tools while 8 are at the
community mobilization stage.
Afar
32
9
7
2 woredas completed service improvement action plans and are
monitoring their implementation; 5 are applying SA tools while 2 are
at the community mobilization stage.
Amhara
166
30
14
15 woredas completed elaboration of service improvement action
plans and are monitoring implementation; 7 are applying SA tools
while 8 are at the community mobilization stage.
Benishan-gul
Gumuz
22
6
4
1 woreda has completed elaboration of service improvement action
plan and is monitoring their implementation.
Dire Dawa
49
4
2
No woreda has completed elaboration of service improvement action
plan; all the 4 are applying SA tools. DD is also one of the few
woredas that need extra hand-holding.
Gambella
13
5
1
No woreda has completed elaboration of service improvement action
plan. Gambella presents a particular case of lagging implementation
but efforts have been made to ensure additional support is provided
over the last quarter.
Harari
9
2
2
1 woreda completed elaboration of service improvement action plan
and is monitoring implementation and 1 is at the community
mobilization stage.
Oromia
304
77
29
27 woredas completed elaboration of service improvement action
plans and are monitoring their implementation; 21 are applying SA
tools while 26 are at the community mobilization stage.
SNNP
157
37
14
20 woredas completed elaboration of service improvement action
plans and are monitoring their implementation; 10 are applying SA
tools while 7 are at the community mobilization stage.
Somali
74
10
3
4 woredas completed elaboration of service improvement action plans
and are monitoring their implementation; 1 is at interface meeting
stage and 5 are applying SA tools. Somali region has significantly
improved progress over the last six months.
Tigray
46
25
6
9 woredas completed elaboration of service improvement action plans
and are monitoring their implementation; 7 are applying SA tools
while 9 are at the community mobilization stage.