Final PBS-ESAP2 Midterm Review Report sent to GoE July17

 
Table 2: ESAP2 Coverage and SAIPs Progress in Summary – On 1
st
and 2
nd
cohort implementation variations, refer to annex 3 
Region 
Woredas (all) 
Woredas 
(ESAP2) 
SAIPs 
(#) 
Salient characteristics on implementation status 
Addis Ababa
116 
18 

1 woreda completed service improvement action plan and is 
monitoring implementation; 9 are applying SA tools while 8 are at the 
community mobilization stage. 
Afar
32 


2 woredas completed service improvement action plans and are 
monitoring their implementation; 5 are applying SA tools while 2 are 
at the community mobilization stage. 
Amhara
166 
30 
14 
15 woredas completed elaboration of service improvement action 
plans and are monitoring implementation; 7 are applying SA tools 
while 8 are at the community mobilization stage. 
Benishan-gul 
Gumuz 
22 


1 woreda has completed elaboration of service improvement action 
plan and is monitoring their implementation. 
Dire Dawa 
49 


No woreda has completed elaboration of service improvement action 
plan; all the 4 are applying SA tools. DD is also one of the few 
woredas that need extra hand-holding. 
Gambella 
13 


No woreda has completed elaboration of service improvement action 
plan. Gambella presents a particular case of lagging implementation 
but efforts have been made to ensure additional support is provided 
over the last quarter.
Harari 



1 woreda completed elaboration of service improvement action plan 
and is monitoring implementation and 1 is at the community 
mobilization stage. 
Oromia
304 
77 
29 
27 woredas completed elaboration of service improvement action 
plans and are monitoring their implementation; 21 are applying SA 
tools while 26 are at the community mobilization stage. 
SNNP 
157 
37 
14 
20 woredas completed elaboration of service improvement action 
plans and are monitoring their implementation; 10 are applying SA 
tools while 7 are at the community mobilization stage. 
Somali
74 
10 

4 woredas completed elaboration of service improvement action plans 
and are monitoring their implementation; 1 is at interface meeting 
stage and 5 are applying SA tools. Somali region has significantly 
improved progress over the last six months. 
Tigray
46 
25 

9 woredas completed elaboration of service improvement action plans 
and are monitoring their implementation; 7 are applying SA tools 
while 9 are at the community mobilization stage. 

Yüklə 0,58 Mb.

Dostları ilə paylaş:
1   ...   5   6   7   8   9   10   11   12   ...   28




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin