16
A Guidebook on Public-Private Partnership in Infrastructure
It is also important at this stage to consider the government stake in the
proposed project. Considering the public good nature
of infrastructure projects, their
strategic importance, effects on other sectors, public safety and security, and
utilization of natural resources, the government has an important
stake in all such
projects. How a PPP project may satisfy these requirements needs to be carefully
examined.
C. THE PPP PROCESS IN THE COUNTRY
The implementation of PPP projects may require the involvement of several
public authorities at various levels of government. A project may require approvals at
several stages by many different authorities. The authority for final approval and
award of PPP contracts is generally centralized. This may
be a special body set up
for this purpose and is usually at the ministerial or council of ministers level.
The whole process of project development, approval and implementation
should be clearly understood by the implementing agency at the outset. In some
countries, the process, activities at various stages of the process and requirements
for approval by the competent authority are all well defined.
The implementing
agency just follows them.
In other countries, however, these elements may not be defined or may be
only partially defined. In such a case, the implementing agency in consultation with
the concerned authorities may consider to:
• Determine the administrative, legal and regulatory
requirements for the
project.
• Map out the whole PPP process.
• Identify tasks involved at each stage of the process.
• Set clear definitions and procedures of the tasks to be undertaken at each
stage, and
• Find out the approvals that may be required and possible requirements
and criteria for such approvals.
The above activities would give a clear idea about the entire project
development and implementation process, amount of work involved in each stage,
and the likely requirements of human and financial resources.
Table 2 provides some guidance in developing a PPP project.
The activities at
different stages in project development, as mentioned in the table, are discussed in
Chapters 3 through 6.
Any previous experience of the concerned implementing agency or any other
agency in the government in implementing PPP projects can greatly help in mapping
out the whole process and in establishing the requirements and approval criteria.
A process flow diagram showing all
the stages and their linkages, and tasks to
be accomplished at each stage can help to understand the whole process by all
A Guidebook on Public-Private Partnership in Infrastructure
17
persons involved in the project. The diagram can also help to estimate human and
other resource requirements in project development.