Progress against milestones

The ODA sets out in advance the milestones it plans to achieve for different phases of the project, to ensure transparency and accountability. In July 2009, the ODA published the 10 milestones that it planned to achieve by 27 July 2010 – the date two years from the Opening Ceremony of the London 2012 Olympic Games. These milestones and progress against them are set out below.


Milestone 1

The structure of the Olympic Stadium, including the roof, will be complete. The first seats will be fitted and work on the field of play about to start.