Quarterly Economic Report



Yüklə 161,09 Kb.
səhifə21/38
tarix10.01.2022
ölçüsü161,09 Kb.
#99425
1   ...   17   18   19   20   21   22   23   24   ...   38
Progress: On track

The earthworks for the wetland areas in the north of the Olympic Park have started, ready for planting to begin in the coming weeks. A contractor has been appointed to landscape the south of the Park. The first of 4,000 semi-mature trees was planted in November 2009.

Construction is now underway on more than two-thirds of the bridges and underpasses that are being built, including the Central Park bridge, which spans the River Lea at a focal point between the Olympic Stadium and Aquatics Centre. More than half the bridges and underpasses have already been structurally completed.

Milestone 9

The Energy Centre, Primary Substation, main sewer and Deep Sewer Pumping Station will all be operational.



Yüklə 161,09 Kb.

Dostları ilə paylaş:
1   ...   17   18   19   20   21   22   23   24   ...   38




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin