Progress: On track
The Olympic Park’s Primary Substation (pictured) was switched on in autumn 2009 and is already supplying power to the Stratford City development. Equipment has been installed inside the Energy Centre and work has begun on the outside of the building’s structure.
The Deep Sewer Pumping Station and main sewer are operational and the electricity network that has been installed across the Park has ‘gone live’.
Milestone 10
All major transport improvements will be in progress or complete, and the next level of detailed planning for transport operations during the Games will have been completed.