1 FOR PRINT UNION BID DOC

Interim Payment

          1. Unless otherwise specified in the SCC, the Contractor shall submit monthly statement for interim payment to the Engineer at the end of each period referred to in GCC Clause 64.7 in a form approved by the Engineer. The monthly statement shall include the following items, as applicable:
(xxxxxxxxx)The estimated contract value of the permanent works implemented up to the end of the period in question;
(yyyyyyyyy)An amount reflecting any price adjustment pursuant to GCC Clause 62;
(zzzzzzzzz)An amount to be withheld as retention sum under GCC Clause 61;
(aaaaaaaaaa)Any credit and/or debit for the period in question in respect of plant and materials on Site intended for, but not yet incorporated in, the permanent works in the amount and under the conditions set out in GCC Clause 64.2;
(bbbbbbbbbb)An amount to be deducted on account of the advance payment repayment under the provisions of GCC Clause 60; and
(cccccccccc)Any other sum to which the Contractor may be entitled under the Contract.
          1. The Contractor shall be entitled to such sums as the Engineer may consider proper in respect of plant and materials intended for, but not yet incorporated in, the permanent works provided that:
(dddddddddd)The plant and materials conform with the specifications for the permanent works and are set out in batches in a way that they may be recognized by the Engineer;
(eeeeeeeeee)Such plant and materials have been delivered to the Site, and are properly stored and protected against loss or damage or deterioration to the satisfaction of the Engineer;
(ffffffffff)The Contractor's record of requirements, orders, receipts and use of plant and materials under the contract are kept in a form approved by the Engineer and such records are available for inspection by the Engineer;
(gggggggggg)The Contractor submits with his statement, the estimated value of the plant and materials on Site together with such documents as may be required by the Engineer for the purpose of valuation of the plant and materials and providing evidence of ownership and payment therefore; and
(hhhhhhhhhh)Where the SCC so provide, ownership of the plant and materials referred to in GCC Clause 83 shall be deemed to be vested in the Public Body.
          1. Approval by the Engineer of any interim payment certified by him in respect of plant and materials pursuant to this GCC Clause shall be without prejudice to the exercise of any power of the Engineer under the Contract to reject any plant or materials which are not in accordance with the provisions of the Contract.
          2. The Contractor shall be responsible for any loss or damage to, and for the cost of storing and handling of, such plant and materials on site and shall effect such additional insurance as may be necessary to cover the risk of such loss or damage from any cause.
          3. Within 30 days of receipt of the said statement for interim payment, it shall be approved or amended in such manner that, in the Engineer's opinion, the application reflects the amount due to the Contractor in accordance with the Contract. In cases where there is a difference of opinion as to the value of an item, the Engineer's view shall prevail. On determination of the amount due to the Contractor, the Engineer shall, within the same 30 days deadline, issue and transmit to the Public Body for payment and to the Contractor for information, an Interim Payment Certificate for the amount due to the Contractor and shall inform the Contractor of the works for which payment is being made.
          4. The Engineer may, by an Interim Payment Certificate, make any corrections or modifications to any previous certificate issued by him and shall have power to modify the valuation in or withhold the issue of, any Interim Payment Certificate if the works or any part thereof is not being carried out to his satisfaction.
          5. Unless the SCC provide otherwise, the frequency shall be one interim payment per month.

Yüklə 1,7 Mb.

Dostları ilə paylaş:
1   ...   107   108   109   110   111   112   113   114   ...   140




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2025
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin