Sbd works (ncb)



Yüklə 1,7 Mb.
səhifə135/140
tarix20.05.2023
ölçüsü1,7 Mb.
#127287
1   ...   132   133   134   135   136   137   138   139   140
1 FOR PRINT UNION BID DOC

GCC 70.1

The Scope of Works shall be defined in: CONSTRUCTION OF DIARY FARM. refer the bill of quantity and specification [insert “Section 6, Schedule of Requirements” or indicate where the Scope of Works shall be defined]

GCC 70.2

The Contractor shall carry out the Works at following Sites: [list sites].HARAMAYA woreda
Sites are located at [insert location] and are defined in Drawings No. [insert Drawings No.].

GCC 71.1

The Start Date shall be 14 calendar days after the date of site handover[insert date]

GCC 72.1

The Intended Completion Date for the whole of the Works shall be [insert date]365 calendar days from the date of site hand over

GCC 74.1(j)

The following events shall also be Compensation Events:
(nnnnnnnnnnnn)The Engineer Orders A Delay Or Dose Not Issue Drawings, Specification, Or Instruction Required For Execution Of The Work
On Time;
(oooooooooooo)The Engineer Instructs The Contractor To Uncover Or To Carry Out Additional Tests Up On Work, Which Is Then Found To Have No Defects;
(pppppppppppp)The Engineer Unreasonably Does Not Approve a Subcontract To Be Late;
(qqqqqqqqqqqq)The Advance Payment Is Delayed;
The Engineer Unreasonably delays issuing interim certificate [list additional Compensation Events, if any]

GCC 79.1

The work register shall be: [tick appropriate box]
(i) Required[specify the practical details]; or
(ii) Not required.


Yüklə 1,7 Mb.

Dostları ilə paylaş:
1   ...   132   133   134   135   136   137   138   139   140




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2025
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin