Program of Implementation of Tasks

          1. Completing the work program given as part of the Bid, the Contractor shall within the time stated in the SCC provide the Engineer with a program of implementation of the tasks, broken down by activity and by month and include the following information:
(cccccccc)the order in which the Contractor proposes to carry out the works;
(dddddddd)the time limits within which submission and approval of the drawings are required;
(eeeeeeee)an organization chart containing the names, qualifications and curricula vitae of the staff responsible for the Site,
(ffffffff)a general description of the method including the sequence, by month and by nature which the Contractor proposes to carry out the works;
(gggggggg)a plan for the setting out and organization of the Site, and
(hhhhhhhh)such further details and information as the Engineer may reasonably require.
          1. The Engineer shall return these documents to the Contractor with his approval or any relevant remarks within ten days of receipt, except where the Engineer, within those ten days, notifies the Contractor of his wish for a meeting.
          2. An update of the program shall be a program showing the actual progress achieved on each activity and the effect of the progress achieved on the timing of the remaining work, including any changes to the sequence of the activities.
          3. The Contractor shall submit to the Engineer for approval an updated program at intervals no longer than the period stated in the SCC. If the Contractor does not submit an updated Program within this period, the Engineer may withhold the amount stated in the SCC from the next payment certificate and continue to withhold this amount until the next payment after the date on which the overdue Program has been submitted.
          4. The approval of the program by the Engineer shall not relieve the Contractor from any of his obligations under the contract. The Contractor may revise the program and submit it to the Engineer again at any time. A revised program shall show the effect of modifications and Compensation Events.
          5. No material alteration to the program shall be made without the approval of the Engineer. If, however, the progress of the works does not conform to the program, the Engineer may instruct the Contractor to revise the program and submit the revised program to him for approval.

Yüklə 1,7 Mb.

Dostları ilə paylaş:
1   ...   92   93   94   95   96   97   98   99   ...   140




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2025
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin