The Contractor is responsible to remove all unnecessary materials from the site. [Specify who is to remove demolition materials if not the Contractor]
GCC 52.5
|
[Specify if the design of particular temporary works is the responsibility of the Public Body]
|
GCC 53.1
|
[Specify, if necessary, the arrangements for soil studies]
|
GCC 55.1
|
[Specify whether there is a derogation from GCC Clause 55]
|
GCC 58.1
|
The amount of the Performance Security shall be: [indicate the amount of the Performance Security]
|
GCC 58.4
|
The types of acceptable Performance Securities are: [insert the name and description of Performance Security acceptable to the Public Body].
The currency shall be: [indicate currency of the Contract Security].
|
GCC 58.8
|
Discharge of the Performance Security shall take place: [insert (a) in accordance with GCC Sub-Clause 58.8; or (b) indicate how the Performance Security shall be discharged]
|
|
Payments to the Contractor
|
GCC 59.1
|
All payment to the Contractor under this Contract shall be made in [insert currency].Ethiopian birr
|
GCC 60.1
|
Advance payment [insert “shall be” or “shall not be”] granted to the Contractor, at his request.
|
|