Consultations with municipalities of all the Host Cities and broadcasters on the implementation of the 2010 FIFA World Cup Legacy Plan concluded



Yüklə 419,04 Kb.
səhifə24/65
tarix07.01.2022
ölçüsü419,04 Kb.
#90738
1   ...   20   21   22   23   24   25   26   27   ...   65
Consultations with municipalities of all the Host Cities and broadcasters on the implementation of the 2010 FIFA World Cup Legacy Plan concluded

  • The legacy planning was finalized in January 2011.

  • The Department monitored the Implementation of the Legacy Plan with CoJ, DTI, and Broadcasters on: VandA, IBC and Fan Parks/PVAs.

  • Decommissioning at all stadiums was completed for Telkom, and equipment was removed.

  • The closeout report was completed in January 2011.

X







-

-

Implementation of the Legacy Plan on Future utilisation of ICT infrastructure rolled out for the 2010 FIFA World Cup facilitated

  • The legacy planning was concluded on 14 Jan 2011. All equipment was removed from all World Cup venues and lists of equipment for City of Cape Town and City of Tshwane was finalized.

  • As part of the implementation of the Legacy Plan, Telkom will to connect the remaining 125 Dinaledi schools from remaining legacy equipment and funds.

X







-

-

Facilitation and monitoring of DTT infrastructure roll-out commenced (60% of population coverage)

Implementation of the DTT rollout plan by Sentech was monitored by way of regular progress meetings and through the exchange of correspondence with the project team members to ensure that the rollout target of 60% population coverage was achieved

X







-

-


Yüklə 419,04 Kb.

Dostları ilə paylaş:
1   ...   20   21   22   23   24   25   26   27   ...   65




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin