Method of Incremental Pricing
Clause 3.16(b) of the Code requires an access arrangement to specify how any covered extension or expansion would effect the reference tariff.
Clause 10.4(a)(iii) of the access arrangement provides that the service provider may seek a capital contribution or a surcharge from prospective users. Clause 10.4(c) provides that any covered new facilities will not affect the reference tariff before the next revisions commencement date.
The Commission notes that clause 10.4(c) appears to preclude a roll-in during this regulatory period. In the absence of forecast expansions under section 8.20 of the Code, section 8.15 provides that capital expenditure can only be rolled-in at the commencement of an access period. Clause 10.4(c) is therefore consistent with the Code. Accordingly, while the Commission considers that clauses 10.4(a)(iii) and 10.4(c) meet the requirements of the Code and are acceptable at this time, these clauses may be subject to change in future regulatory periods.
Queuing Policy
-
Code requirements
Sections 3.12 to 3.15 set out the Code’s requirements for a queuing policy. An access arrangement must include a queuing policy for determining the priority given to users and prospective users for obtaining access to a covered pipeline and for seeking dispute resolution (under section 6 of the Code). The purpose of a queuing policy is to allocate spare and developable capacity where there is insufficient capacity to satisfy the needs of all users and potential users that have requested capacity.
A queuing policy must be set out in sufficient detail to enable users and prospective users to understand in advance how it will operate. It must also, to the extent reasonably possible, accommodate the legitimate business interests of the service provider, of users and prospective users, and must generate economically efficient outcomes.
Epic’s proposal
Clause 10 of Epic’s 29 June 2001 access arrangement provides:
-
requests for service will be accorded priority on a first-come-first-served basis and will be dealt with in that order;
-
the service provider may deal with requests for service outside their priority provided that the request/s for service ahead in the queue are not disadvantaged; and
-
there is no automatic right of renewal of a contract in the access arrangement.
-
Submissions by interested parties
Market participants made the following comments in relation to the queuing policy in clause 10 of Epic’s 29 June 2001 access arrangement.
Energy SA and TXU submitted that a first in first served queue was not appropriate.454 The South Australian Government indicated that:
a “first in, first served” policy is not fair and equitable, nor practical from the point of view of good public policy which seeks to produce optimal outcomes for all parties.
TXU was strongly opposed to a first in first served policy on the basis that such a policy:
-
Allocates capacity on a trivial basis which results in capricious outcomes as prospective users who were seconds slower than other users may have to pay substantially higher tariffs.
-
Allocation of capacity on the basis of first in, allows market participants with access to that capacity to exercise market power in circumstances where existing capacity is significantly cheaper than alternative capacity. For example, a party with capacity that it does not require could on sell this gas to prospective users at a premium. Presumably, there is scope for such a ‘wholesaler’ to price up to the cost of incremental expansion.
-
Allows, if not encourages, ambit capacity requests.
-
Does not allow for consideration of the relative commercial merit of a proponent's requirement for gas. Where proponents make ambit requests market signals regarding the true requirements for new capacity are obfuscated.
-
May lead to results which are contrary to the interests of South Australian consumers. For example, if a market participant is able to obtain access to existing capacity it could capture economic rents on that capacity which could ultimately be passed on to consumers.
TXU indicated that the current ‘queue’ for capacity on the MAPS demonstrates its concerns. The MAPS becomes substantially uncontracted in 2006. Epic indicated that it would accord priority for contract negotiations for that period on a first in first served basis. Total requests for gas substantially exceeded the capacity of the pipeline.
Subsequently, TXU notified an access dispute under the Natural Gas Pipelines Access Act (South Australia) 1995 (NGPAA 1995). The NGPAA 1995 provides for an access regime for gas transmission in SA and provides that an access dispute exists if requests for service exceed the capacity of the pipeline. The 1995 South Australian access law was repealed by the GPAL but continues to apply until an access arrangement is approved under the Code.
Potential Energy submitted that clause 10 provided a workable system for prospective users as it allows for prospective users to do the following:455
-
inquire about the availability of capacity and its indicative cost on an informal basis;
-
firm up the availability and cost of capacity without committing to that capacity;
-
retain a position on the queue while feasibility studies are conducted.
NRG Flinders submits that it ‘agrees with the proposed queuing policy.456 TGT indicated that clause 10 was acceptable.457 Origin noted that the first in first served is more flexible and less prescriptive than Epic’s original queuing policy.458
Alternative Queuing Policy
Due to concerns in relation to the operation of a first in first served queue in the current circumstances of the South Australian gas industry, the Commission sought comments from market participants on an alternative queuing policy. The alternative raised by the Commission involved the service provider holding an open season prior to allocating existing capacity. The open season would involve the service provider advertising that spare capacity was available and allowing prospective users to submit a request for service. Where the demand for existing capacity exceeded capacity, capacity would be allocated by negotiation, conciliation or arbitration.
Market participants, including TXU, Energy SA, National Power, AGLES&M, and NRG Flinders supported the proposed queue in principle.459
TXU indicated that the alternative policy was a ‘very positive advance which has the potential to provide benefits both to participants in the South Australian gas market and ultimately to consumers of both gas and electricity in South Australia’.460
Origin indicated that it was an appropriate method to allocate spare capacity to incremental users in circumstances where:461
-
Users with contracts have been given the opportunity to renew their contracts and have decided not to recontract;
-
Existing users’ requirements for gas have been satisfied. Origin consider that the intent of Section 6.15(d) of the Code is that existing users of gas should have priority over incremental users.
A number of parties made comments in relation to the details of the proposed policy, which are outlined below.
Dostları ilə paylaş: |