Background sawep phase 1 (2008 – 2010): Outcome



Yüklə 461 b.
səhifə14/14
tarix07.01.2022
ölçüsü461 b.
#90742
1   ...   6   7   8   9   10   11   12   13   14

Lesson learned (design and process): Coordination with parallel initiatives should be attempted designed into the projects from the beginning, not being the sole responsibility of the project manager during implementation.



  • DoE Executing Agency, UNDP support services, SANEDI program manager support

    • DoE Executing Agency, UNDP support services, SANEDI program manager support

    • USD3.5 mill, USD35 mill co-financing

    • PPG develop over 2013/14

    • Prodoc approved May 2015 to May 2019 (4 years), Prodoc signed Des 2015, PM appointed Aug 2016 (less than 3 years left for implementation)

    • Main Objective: To support progress towards the IRP 2010 target of 8.4 GW (new build) wind capacity by 20130 (updated IRP 2016 37GW wind by 2015)



    Components:Component 1: Monitoring and Evaluation of the implementation of local content requirements

    • Components:Component 1: Monitoring and Evaluation of the implementation of local content requirements

    • Component 2: Resource-mapping and wind corridor development support for policy-makers:

    • Component 3: Support for the development of small-scale wind sector

    • Component 4: Training and human capital development for the wind energy sector





    SAWEP PPG developed 2013/14. Updates and adjustments to SAWEP 2 components, outputs and activities were then identified with key stakeholders prior to and as reported in the Inception Workshop report. The SAWEP Prodoc to be updated accordingly.

    • SAWEP PPG developed 2013/14. Updates and adjustments to SAWEP 2 components, outputs and activities were then identified with key stakeholders prior to and as reported in the Inception Workshop report. The SAWEP Prodoc to be updated accordingly.

    • SAWEP 2 budget does not provide, as in SAWEP 1 for reporting costs (e.g. printing) and also not for Miscellaneous expenses (information banners, pamphlets) nor project workshop e.g. catering costs





    Yüklə 461 b.

    Dostları ilə paylaş:
    1   ...   6   7   8   9   10   11   12   13   14




    Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
    rəhbərliyinə müraciət

    gir | qeydiyyatdan keç
        Ana səhifə


    yükləyin