SA Power Networks proposed $140.0 million ($2014–15) in step changes in its revised proposal. SA Power Networks' revised step changes contribute 9.8 per cent to its total opex forecast. It did not specify why it did not repropose many step changes it proposed in its initial proposal. SA Power Networks' revised proposal on step changes is set out below in Table C. to Table C..
We received several submissions supporting our preliminary position on most step changes. These included submissions from:
Business SA149
Consumer Challenge Panel150
Energy Consumers Coalition of South Australia (ECCSA)151
Energy Retailers Association of Australia (ERAA)152
Origin Energy153
South Australian Council of Social Services (SACOSS).154
Business SA agreed there are few changes to the operating environment facing SA Power Networks during 2015–20 with respect to regulatory obligations. It submitted that while customers may express a preference for certain services, it does not necessarily mean that an increase in total forecast expenditure is required.155
The Consumer Challenge Panel (CCP) agreed that most step changes SA Power Networks proposed were already captured by base opex or output growth.156 It also considered there should be a negative step change for vegetation management.157
Table C. Legal and regulatory step changes ($ million, 2014–15)
Proposal
|
SA Power Networks initial proposal
|
AER preliminary decision
|
SA Power Networks revised proposal
|
AER final decision
|
Asset inspections - no access poles
|
23.4
|
-
|
21.9
|
-
|
Asset inspections - underground cables
|
3.1
|
-
|
-
|
-
|
Asset inspections - bushfire inspection frequency
|
15.6
|
-
|
12.9
|
-
|
WH&S - Asset inspections 2 person crews
|
2.8
|
-
|
2.8
|
-
|
WH&S - Network operations
|
4.0
|
-
|
-
|
-
|
WH&S - Fleet monitoring
|
2.2
|
-
|
2.2
|
-
|
WH&S - Fleet inspections
|
3.9
|
-
|
3.9
|
-
|
New RIN requirements
|
9.2
|
-
|
6.4
|
6.4
|
National Energy Retail Law Regulations
|
4.3
|
-
|
-
|
-
|
National Energy Customer Framework
|
1.3
|
1.3
|
1.3
|
1.3
|
Demand Side Participation
|
33.8
|
-
|
13.3
|
5.1
|
Environmental Management
|
1.4
|
-
|
-
|
-
|
Total
|
105.0
|
1.3
|
64.8
|
12.7
|
Source: SA Power Networks, Reset RIN 2015–20; AER, Opex model for SA Power Networks - preliminary decision; SA Power Networks, Revised Reset RIN 2015–20; AER, Opex model for SA Power Networks ─ final decision.
Table C. Capital program impact step changes ($ million, 2014–15)
Proposal
|
SA Power Networks initial proposal
|
AER preliminary decision
|
SA Power Networks revised proposal
|
AER final decision
|
Information Technology
|
43.9
|
-
|
19.4
|
4.0
|
Mobile radio
|
7.9
|
7.9
|
12.8
|
12.8
|
Carrier costs, radio licensing and planning
|
5.1
|
-
|
-
|
-
|
Network Management Centre
|
3.6
|
-
|
-
|
-
|
Data quality
|
3.9
|
-
|
3.9
|
-
|
Substation maintenance - disconnectors
|
2.4
|
-
|
-
|
-
|
Flexible load management
|
1.0
|
-
|
|
-
|
Total
|
69.6
|
7.9
|
36.1
|
16.7
|
Source: SA Power Networks, Reset RIN 2015–20; AER, Opex model for SA Power Networks - preliminary decision; SA Power Networks, Revised Reset RIN 2015–20; AER, Opex model for SA Power Networks - final decision.
Table C. Customer driven initiatives and changing community expectations ($ million, 2014–15)
Proposal
|
SA Power Networks initial proposal
|
AER preliminary decision
|
SA Power Networks revised proposal
|
AER final decision
|
Change in NBFRA trimming cycle
|
13.5
|
-
|
13.5
|
-
|
Tree removal and replacement - BFRA
|
9.2
|
-
|
10.5
|
-
|
Tree removal and replacement - NBFRA
|
6.1
|
-
|
6.1
|
-
|
Advanced tree trimming practices
|
1.9
|
-
|
1.9
|
-
|
Community engagement and consultation - vegetation management
|
1.2
|
-
|
1.2
|
-
|
Customer education and consultation
|
1.7
|
-
|
1.7
|
-
|
Self-service products
|
1.0
|
-
|
1.0
|
-
|
Customer service team
|
1.6
|
-
|
1.6
|
-
|
Bushfire education campaign
|
2.6
|
-
|
2.6
|
-
|
Extreme weather education campaign
|
1.9
|
-
|
1.9
|
-
|
Farmers and sailors - education campaign
|
0.9
|
-
|
0.9
|
-
|
Total
|
41.6
|
-
|
42.8
|
-
|
Source: SA Power Networks, Reset RIN 2015–20; AER, Opex model for SA Power Networks - preliminary decision; SA Power Networks, Revised Reset RIN 2015–20; AER, Opex model for SA Power Networks ─ final decision.
Table C. Finance related operating expenditure ($ million, 2014–15)
Proposal
|
SA Power Networks initial proposal
|
AER preliminary decision
|
SA Power Networks revised proposal
|
AER final decision
|
Insurance premiums
|
3.0
|
-
|
-
|
-
|
Superannuation
|
–2.4
|
-
|
-
|
-
|
Total
|
0.6
|
-
|
-
|
-
|
Source: SA Power Networks, Reset RIN 2015–20; AER, Opex model for SA Power Networks - preliminary decision; SA Power Networks, Revised Reset RIN 2015–20; AER, Opex model for SA Power Networks ─ final decision.
Table C. Base year adjustments ($ million, 2014–15)
Proposal
|
SA Power Networks initial proposal
|
AER preliminary decision
|
SA Power Networks revised proposal
|
AER final decision
|
Regulatory proposal
|
–8.2
|
-
|
-
|
-
|
Distribution licence fee
|
–5.5
|
–5.0
|
–5.0158
|
–5.0
|
Non network solution
|
1.3
|
-
|
1.3159
|
-
|
Property
|
2.0
|
-
|
-
|
-
|
Total
|
–10.4
|
–5.0
|
–3.7
|
–5.0
|
Source: SA Power Networks, Reset RIN 2015–20; AER, Opex model for SA Power Networks - preliminary decision; SA Power Networks, Revised Reset RIN 2015–20; AER, Opex model for SA Power Networks ─ final decision.