The mortar to be used for pointing shall be in 1 part of cement to two parts of fine aggregate complying with BS 1199 of Table 2.
The raked out joints of walls shall be flush or recess pointed as indicated on drawings. Flush pointing shall be finished even & level with the surface of the wall material.
Recess pointed surfaces shall have the raked out joints pointed with struck weathered horizontal joints and square recessed vertical joints with a depth of not less than 5mm or as shown on drawings.
Pointed surfaces shall be cement dusted or cement paste applied to form final even & smooth surfaces. Pointed walls shall be wetted for at least seven days and allowed to cure for at least 28 days before further finish is applied.