Sierra Leone
Energy and mining
(R) SL: Western Area Power Generation Project: In May 2014 the Government of Sierra Leone requested IDA for a guarantee for the proposed Western Area Power Generation Project (WAPGP) to be developed as an independent power producer selling to electricity the Electricity Distribution and Supply Authority (EDSA).
WAPGP is part of the Government’s plan for private sector participation in the generation subsector to meet electricity demand. The Project is proposed as a 128 MW Heavy Fuel Oil (HFO) fired power plant to be located on an existing industrial site about 4 km outside Freetown. The Project is to be constructed in phases over three to four years, of which the first phase is 50MW. Approval completed on 14 July 2016. Environmental Assessment Category B. Project: P153805. US$ 40.0 (GUID). Consulting services to be determined. Implementing agency(ies) to be determined.
Dostları ilə paylaş: |