A guidebook on public-private partnership in infrastructure


Supply and management contracts



Yüklə 0,66 Mb.
Pdf görüntüsü
səhifə9/72
tarix13.04.2023
ölçüsü0,66 Mb.
#125245
1   ...   5   6   7   8   9   10   11   12   ...   72
ESCAP-2011-MN-Guidebook-on-PPP-infrastructure

Supply and management contracts 
A management contract is a contractual arrangement for the management of 
a part or whole of a public enterprise (for example, a specialized port terminal for 
container handling at a port or a utility) by the private sector. Management contracts 
allow private sector skills to be brought into service design and delivery, operational 
control, labour management and equipment procurement. However, the public sector 
retains the ownership of facility and equipment. The private sector is assigned 
specified responsibilities concerning a service and is generally not asked to assume 
commercial risk.
The private contractor is paid a fee to manage and operate services. 
Normally, the payment of such fees is performance-based. Usually, the contract 
period is short, typically three to five years
4
. But the period may be longer for large 
and complex operational facilities such as a port or an airport.
The main pros and cons of this model include the following: 
Pros: 
• Can be implemented in a short time. 
• Least complex of all PPP models. 
• In some countries, politically and socially more acceptable for certain 
projects (such as water projects and strategic projects like ports and 
airports). 
Cons: 
• Efficiency gains may be limited and little incentive for the private sector to 
invest.
• Almost all risks are borne by the public sector. 
• Applicable mainly to existing infrastructure assets.
Turnkey 
Turnkey is a traditional public sector procurement model for infrastructure 
facilities. Generally, a private contractor is selected through a bidding process. The 
private contractor designs and builds a facility for a fixed fee, rate or total cost, which 
is one of the key criteria in selecting the winning bid. The contractor assumes risks 
involved in the design and construction phases. The scale of investment by the 
4.
For example, the initial management contract for Port Klang in Malaysia with a foreign company was only for 
three years. The main purpose was to set-up the system so that eventually a local company could take over 
for a longer period. 


A Guidebook on Public-Private Partnership in Infrastructure 

 
private sector is generally low and for a short-term. Typically, in this type of 
arrangement, there is no strong incentive for early completion of the project. This 
type of private sector participation is also known as Design-Build.
The main pros and cons of this model include the following: 
 Pros: 
• Well understood traditional model.
• Contract agreement is not complex. 
• Generally, contract enforcement is not a major issue. 
 Cons: 
• The private sector has no strong incentive for early completion. 
• All risks except those in the construction and installation phases are borne 
by the public sector. 
• Low private investment for a limited period.
• Only limited innovation may be possible. 

Yüklə 0,66 Mb.

Dostları ilə paylaş:
1   ...   5   6   7   8   9   10   11   12   ...   72




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin