Quarterly Economic Report



Yüklə 161,09 Kb.
səhifə16/38
tarix10.01.2022
ölçüsü161,09 Kb.
#99425
1   ...   12   13   14   15   16   17   18   19   ...   38
Progress: On track

The Velodrome’s lower tiers and the steelwork supporting the track were completed at the end of 2009. The upper tiers and the structural steelwork that give the roof its distinctive double curves have also been finished. The venue’s cable-net roof has been lifted into place.


Milestone 4

The structure of the International Broadcast Centre (IBC) and multi-storey car park will be finished, with roof and wall cladding well underway. The Main Press Centre’s (MPC) structure will be nearing completion.


Progress: On track

The structure of the IBC was finished in late summer 2009 and the cladding of the building has now been completed. The structure of the MPC has reached its full height, with work underway on the top floor of the building. The frame of the multi-storey car park has been finished.


Milestone 5

The Handball Arena and Basketball Arena structures will be in place, with internal works underway. Building work will have begun on the new Eton Manor sporting facilities.



Yüklə 161,09 Kb.

Dostları ilə paylaş:
1   ...   12   13   14   15   16   17   18   19   ...   38




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin