National Academies study “Setting Priorities for Large Research Facility Projects” (Brinkman report) makes specific recommendations for prioritizing, planning, and overseeing the construction and operation of large facilities supported by NSF
The report cites the need to make greater resources available for pre-award planning of a project’s workscope
Implement rigorous post-award oversight through periodic external review
Embraces NAS recommendations for greater clarity and transparency to selection and prioritization process
NSF will take steps to enhance the robustness of the pre-construction project development process to improve cost projections for facilities recommended for construction
NSF Roadmap
NSF is now developing a Facility Plan (the “roadmap”)
Report of projects in construction and various stages of development
Includes detailed discussion of the development plans and criteria for projects in advanced stage of pre-construction development
Discussion of the scientific objectives and opportunities that provide the context and compel the need for their development
Will provide discussion of overarching considerations used for cross-disciplinary prioritization (first and second NAS ranking criteria)
Facility Plan will be a public document, updated annually by NSF Director
Facility Plan should become a strategic tool for communicating with research communities and government policy makers
First public draft of plan expected in April or May, 2005 following March NSB meeting
Expect to post for public comment
Process of Large Facility Project Development
Revises existing process defined in NSF’s Facilities Management and Oversight Guide: http://www.nsf.gov/pubs/2003/nsf03049/nsf03049.pdf
Defines a new stage in the pre-construction development process:
“Readiness Stage”:
Has well defined entrance and exit gates
Entrance requires formally defined and publicly distributed development plan
Readiness Stage Development plan included in NSF’s Facility Plan
Functional requirements, definition of systems and functional areas.
Large cost uncertainty.
About 1/3 of total design effort.
Preliminary design
Site-specific design. Principal components, types of equipment, members, sizes defined.
Cost uncertainty much reduced, roughly 25% larger than final design cost uncertainty.
About 1/3 of total design effort.
Final design
Interconnections of components defined. Component vendors defined. Mounting and installation defined.
About 1/3 of total design effort.
Coordination with initiatives in other agencies
Want to make sure that Facilities Plan and the NSF’s Management and Oversight Guide broadly mesh NSF’s strategic planning with activities in other agencies – DOE, NASA
Incorporate project-specific factors, criteria, timing of inter-agency coordination within development plans – will be published as components of Facilities Plan
Natural place to articulate NSF’s intentions for specific international partnerships
Next steps in revision of Facilities Management and Oversight Guide
Identify specific implementation steps that support principles promulgated in NSB/NSF report
NSB review
Expect a period for public reaction and comment
Useful to have advisory committee input on these issues and other problems that exist in current Facilities Guide
Backup materials
NAS Study Findings
“There is a lack of funding for disciplines to conduct idea-generating and project-ranking activities and, once ideas have some level of approval, a lack of funding for conceptual development, planning, engineering, and design—information needed when judging whether a project is ready for funding in light of its ranking and for preparing a project for funding if it is selected”.
More planning resources will:
Reduce uncertainties in construction and operations budgets
Reduce uncertainty in construction schedule
Reduce likelihood of de-scoping
Thorough pre-construction risk assessment will create a more robust Project Execution Plan
Create an appropriate framework for cooperation for activities involving international and inter-agency partnerships as an integral part of in-depth planning.
Make project oversight during construction more straightforward, add more definition to the proposed workscope and decision points.
Allow more in-depth consideration of transition to operations and greater certainty in predicted O&M costs.
Avoid a funding hiatus. Overlap some development activities beyond NSB approval and inclusion in annual NSF budget submission.
NSF/NSB Report:
“The National Academies’ Report properly calls attention to the necessity for considerable pre-approval funding for planning and development when it questions whether there is sufficient NSF support for this "bottom up" process. NSF endorses the Report’s recommendations to provide researchers access to funding sufficient to develop compelling research agendas, to refine and prioritize their facility requirements, and to complete research and development on facility designs and needed technologies. The level and form of funding for planning and development will be reviewed, and an evaluation will be made of how project funds are best invested to attain robust plans and schedules with better cost projections, so that only well-defined and thoroughly-costed projects are brought forward for consideration by the Board.”
More NSF/NSB Report:
“The Director and the Board recognize the need to strengthen oversight of the implementation of large facility projects, which will require increased investments of NSF staff time and travel funds. The Report emphasizes the importance of initial planning and definition of technical scope, budget, and schedule, followed by periodic post-award status reviews held on-site by external experts, with implementation of a transparent process for management of changes to a project’s implementation plan.”