Contents 3
Shortened forms 14
1Review framework 15
1 Overview of the service provider 15
1Overview of the service provider 15
1.1Regulation prior to 1 July 2008 16
2 The relevant requirements of the NGL and the NGR 16
2The relevant requirements of the NGL and the NGR 16
2.1Access arrangement proposal to be approved in its entirety or not at all 18
3 Access arrangement review process 18
3Access arrangement review process 18
3.1Revision of access arrangement proposal and commencement of public consultation following draft decision 19
3.2Final decision 20
3.3Further final decision 20
4 Time limits on AER decision making 20
4Time limits on AER decision making 20
5 Public consultation 21
5Public consultation 21
5.1Protected information submitted to the AER 22
2Pipeline services 23
6 Final decision 23
6Final decision 23
7 Revised proposal 23
7Revised proposal 23
8 Assessment approach 24
8Assessment approach 24
9 Reasons for decision 24
9Reasons for decision 24
3Capital base 28
10 Final decision 28
10Final decision 28
11 Revised proposal 30
11Revised proposal 30
12 Assessment approach 31
12Assessment approach 31
13 Reasons for decision 31
13Reasons for decision 31
13.1Opening capital bases at 1 January 2008 32
13.2Opening capital bases at 1 January 2013 32
13.3Projected capital bases at 31 December 2017 33
13.4Depreciation approach to capital base roll forward at the next access arrangement review 33
14 Revisions 35
14Revisions 35
4Capital expenditure 36
15 Final decision 36
15Final decision 36
15.1Conforming capital expenditure for 2007–11 36
15.2Conforming capital expenditure for the 2013–17 access arrangement period 37
16 Revised proposal 43
16Revised proposal 43
16.12013–17 access arrangement period 43
17 Assessment approach 45
17Assessment approach 45
18 Reasons for decision 45
18Reasons for decision 45
18.1Mains replacement 48
18.2Connections 75
.1 The contract price for undertaking each component of a connection in each contracting region. 82
.2 Any changes in the nature of connections work. This could include: 82
18.3Meter replacement 88
18.4Augmentation 94
18.5Information Technology (IT) 97
18.6SCADA 101
18.7Other non-demand 103
18.8Extensions 111
18.9Overheads 112
18.10Government and customer contributions 114
19 Adjustments to labour and material escalation 115
19Adjustments to labour and material escalation 115
20 Adjustments for Envestra's proposed network management fee 116
20Adjustments for Envestra's proposed network management fee 116
21 Equity raising costs 118
21Equity raising costs 118
21.1Benchmark equity raising costs 119
22 Revisions 122
22Revisions 122
5Rate of return 123
23 Final decision 123
23Final decision 123
23.1AER process 126
23.2Overview of reasons 127
24 Assessment approach 130
24Assessment approach 130
24.1Requirements of the national gas law and rules on the rate of return 131
24.2Selection of well accepted approach and model 133
24.3Selection of a well accepted approach and model 134
24.4Approach to the determination of specific parameters 134
24.5Reasonableness check on overall rate of return 135
24.6Promotion of regulatory certainty and consistency 135
25 Reasons for final decision 136
25Reasons for final decision 136
25.1The Capital Asset Pricing Model (CAPM) 136
25.2Risk free rate 137
25.3Market risk premium 144
25.4Equity beta 160
25.5Debt risk premium 161
25.6Forecast inflation 162
25.7Gearing ratio 162
25.8Reasonableness checks on overall rate of return 163
26 Revisions 164
26Revisions 164
6Depreciation 165
27 Final decision 165
27Final decision 165
28 Revised proposal 166
28Revised proposal 166
29 Assessment approach 167
29Assessment approach 167
30 Reasons for decision 167
30Reasons for decision 167
30.1Standard economic lives 167
30.2Remaining economic lives 168
31 Revisions 168
31Revisions 168
7Operating expenditure 170
32 Final decision 170
32Final decision 170
32.1Envestra Victoria 170
32.2Envestra Albury 170
33 Revised proposal 171
33Revised proposal 171
34 Assessment approach 172
34Assessment approach 172
35 Reasons for decision 172
35Reasons for decision 172
.1 First, increased demands for Envestra's outputs may require it to expand its network. It is reasonable that an efficient service provider will require more inputs, and thus greater opex, to deliver more output. It therefore is reasonable to assume it needs an allowance for network growth. 173
.2 Second, it is reasonable to assume that the cost of inputs for an efficient firm to produce the same level of output may not change at the same rate as CPI. Consequently it is reasonable to account for real cost changes in Envestra's inputs. However, to the extent the cost of inputs change, the input mix which minimises costs will also likely change. Thus, to apply input cost escalation while assuming a constant input mix will provide at least the efficient costs of a prudent service provider. 173
.3 Third, there may be other reasons beyond Envestra's control that will increase or decrease its costs. For example, regulatory obligations may change requiring Envestra to increase expenditure to meet those new obligations. For this reason the AER allows for other incremental increases above base year opex (often referred to as step changes). Generally step changes should only be provided for cost increases beyond the service provider's control. Otherwise the step change would represent an increase in costs to produce the same level of output and thus a loss in efficiency. 173
35.1Forecasting base year 175
.1 remove movements in provisions (Victoria only) 175
.2 add payments made from provisions (Albury only) 175
.3 remove licence fees 175
35.2Network growth 177
35.3Escalation of base year opex 177
35.4Step changes 178
.1 regional SCADA 178
.2 IT–road map initiative 178
.3 extensions to new towns 178
.4 knowledge management 178
.1 pipeline integrity remediation works 179
.2 pipeline signage replacement 179
.3 holes in meter boxes 179
.4 pipe saddle support repairs 179
.5 gas pipes in drains 179
.6 easement vegetation management 179
.1 cost of carbon 179
.2 network monitoring and control 179
.3 interval meter data management 179
.4 graphical information system analyst 179
.5 increased maintenance rates 179
.6 increase in insurance costs 179
.7 change in regulatory policy—reactive mains replacement 179
.8 National Energy Customer Framework (NECF) 179
.9 technical training 180
.10 meter station charges 180
.11 network development 180
.1 regulatory change 181
.2 non-recurrent expenditure 181
.3 discretionary expenditure 181
35.5Assessment of proposed step changes 184
.1 Based on recent capital costs of installing Traralgon CTM station, it considered APA GasNet's quotes to be reasonable. 196
.2 Historical capital costs for CTM stations are no longer relevant due to real cost increases. 196
.3 It considered it would not be reasonable or efficient to incur considerable expense in questioning APA GasNet's quotes at this stage, because they are budget estimates only, and detailed costs will be reviewed as the project advances. Envestra considered its approach to obtaining initial quotes and then obtaining final quotes at a later stage just before implementation is consistent with good industry practice when planning capital works. 196
.4 Because the construction of CTMs is core business for APA GasNet, Envestra considered that APA GasNet's quotes provide the best forecast of CTM capital costs. 197
.5 Previous AER regulatory reviews would confirm that GasNet is a prudent and efficient service provider. Envestra also believed that such costs would also benchmark well against other similar projects approved by the AER in previous review processes and against any further engineering analysis that the AER might consider appropriate. 197
.1 The Traralgon CTM station is significantly different to the new stations proposed by Envestra. The AER notes that the transmission pipeline service for the Traralgon station is thirteen times longer than those estimated for the new Pakenham, Wollert and Clyde North stations. As a result, the AER considers the capital cost for the new Traralgon station is not comparable to the forecast capital cost for Pakenham, Wollert and Clyde North stations. 197
.2 The AER considers that recent real cost increases do not explain such a large increase in APA GasNet's underlying costs. Meter installations are composed of labour costs and materials costs. Based on the wage price index, labour costs associated with the gas industry have only increased by 4.2 per cent in real terms since 2007. The AER notes that the real cost of some materials associated with the gas pipeline industry fell in real terms over the period 2009–2012. The AER also notes that APA GasNet did not propose materials real cost escalation for the 2013–17 access arrangement period. If APA GasNet considered that materials were rising faster than the consumer price index, then it is reasonable to assume APA GasNet would have proposed materials real cost escalation in its recent access arrangement proposal. The increase, or lack thereof, in real labour and materials costs for transmission pipelines indicate that real cost increases do not account in APA GasNet's forecast increase in the costs to install or upgrade a meter station. 197
.3 The AER recognises that quotes are refined closer to the date the project is implemented, and, and as a result, the actual cost of projects often differ from the forecast cost. However, this is true of any forecast. The AER must be satisfied that the forecast was arrived at on a reasonable basis and is the best estimate in the circumstance. The AER considers that a prudent service provider would question such large increase in the price that it receives from a supplier, even if were an initial quote. Accepting such a large increase in costs without question, regardless of the competencies of the supplier, is not a forecast arrived at on a reasonable basis, is not the best estimate possible in the circumstances, and would not be consistent with good industry practice. 197
.4 For similar reasons as set out in point 3 above, the AER considers that a prudent service provider would not accept such a large increase in price on the basis that the nature of APA GasNet's core business is construction. 198
.5 APA GasNet's CTM facilities are not regulated by the AER. It is Envestra's CTM charges which the AER is regulating. Therefore the most relevant information that the AER has access to about CTM capital costs is the information that Envestra has provided to the AER about the capital costs of installing and upgrading CTM facilities. Given the quotes APA GasNet provided to Envestra are significantly above the historical costs of installing or upgrading CTMs, the AER considers APA GasNet's forecasts do not benchmark well compared to the historical costs of providing similar services. 198
35.6Network Management Fee and ancillary reference services 202
35.7Debt raising costs and liquidity costs 203
36 Revisions 206
36Revisions 206
36.1Envestra Victoria 206
36.2Envestra Albury 206
8Incentive mechanism 207
37 Final decision 207
37Final decision 207
37.1Carryover from the 2008–12 access arrangement period 207
37.2Incentive mechanism for the 2013–17 access arrangement period 207
38 Revised proposal 208
38Revised proposal 208
38.1Carryovers accrued in the 2008–12 access arrangement period 208
38.2Proposed incentive mechanism for the 2013–17 access arrangement period 208
39 Assessment approach 208
39Assessment approach 208
40 Reasons for decision 209
40Reasons for decision 209
40.1Carryover from the 2008–12 access arrangement period 209
40.2Incentive mechanism to apply in the 2013–17 access arrangement period 210
41 Revisions 212
41Revisions 212
41.1Envestra Victoria 212
41.2Envestra Albury 213
9Corporate income tax 214
42 Final decision 214
42Final decision 214
43 Revised proposal 216
43Revised proposal 216
44 Assessment approach 217
44Assessment approach 217
45 Reasons for decision 217
45Reasons for decision 217
45.1Opening tax asset base as at 1 January 2013 217
45.2Tax depreciation approaches 218
45.3Standard tax asset lives 219
45.4Remaining tax asset lives 220
45.5Utilisation of imputation credits (gamma) 221
46 Revisions 221
46Revisions 221
10Demand 222
47 Final decision 222
47Final decision 222
48 Revised proposal 222
48Revised proposal 222
49 Assessment approach 222
49Assessment approach 222
50 Reasons for decision 222
50Reasons for decision 222
50.1Normal Weather – the choice of EDD inputs (Victorian network) 222
50.2Normal Weather – the choice of HDD inputs (Albury network) 224
50.3Other issues 225
50.4Conclusion 225
51 Revisions 226
51Revisions 226
11Tariff setting 227
52 Final decision 227
52Final decision 227
53 Revised proposal 227
53Revised proposal 227
54 Assessment approach 227
54Assessment approach 227
55 Reasons for decision 227
55Reasons for decision 227
56 Revisions 228
56Revisions 228
12Tariff variation mechanism 229
57 Final decision 229
57Final decision 229
58 Revised proposal 230
58Revised proposal 230
59 Assessment approach 230
59Assessment approach 230
60 Reasons for decision 231
60Reasons for decision 231
60.1Annual tariff variation mechanism 231
60.2Costs pass through mechanism 236
.1 The first amendment applies the insurance cap event to not only costs beyond the relevant policy limit (as in the AER's draft decision) but also to losses (amendment to factor (b)). 236
.2 The second amendment applies the insurance cap event not only to reference services (as in the AER's draft decision) but also to non-reference services (amendment to factor (c)). 237
60.3Procedure for oversight and approval of tariff variation 245
61 Revisions 249
61Revisions 249
13Non-tariff components 260
62 Final decision 260
62Final decision 260
63 Terms and conditions 260
63Terms and conditions 260
63.1Final decision 260
63.2Revised proposal 261
63.3Assessment approach 261
63.4Reasons for decision 261
64 Capacity trading requirements 294
64Capacity trading requirements 294
64.1Final decision 294
64.2Revised proposal 294
64.3Assessment approach 294
64.4Reasons for decision 294
65 Queuing arrangements 294
65Queuing arrangements 294
65.1Final decision 294
65.2Revised proposal 294
65.3Assessment approach 294
65.4Reasons for decision 294
66 Extension and expansion requirements 295
66Extension and expansion requirements 295
66.1Final decision 295
66.2Revised proposal 295
66.3Assessment approach 295
66.4Reasons for decision 295
67 Terms and conditions for changing receipt or delivery points 296
67Terms and conditions for changing receipt or delivery points 296
67.1Final decision 296
67.2Revised proposal 297
67.3Assessment approach 297
67.4Reasons for decision 297
68 Review dates 297
68Review dates 297
68.1Final decision 297
68.2Revised proposal 297
68.3Assessment approach 297
68.4Reasons for decision 297
69 Amendments 298
69Amendments 298