03224 Delivery & Storage

Formwork material shall be delivered to the site immediately after taking over the site. Formwork timber and panels shall be open stacked in an off the ground position. Timber for formwork shall be stored under shed.


Timber and panel formwork for reuse shall be cleaned, oiled & stacked.
0323 PRODUCT

Formwork material shall be sawn board reasonably straight grained, plywood or metal panel the use of which shall be determined in compliance with the type of surface finish required.


0324 EXECUTION
03241 General

Forms shall be used, wherever necessary to confine the concrete and mould it to the required dimensions and shapes.


Forms shall be sufficiently tight to sustain loss of liquid from the concrete. Backup material at joints to prevent leakage and fins shall be provided as required. Formwork material shall be of sufficient thickness to withstand pressure of newly placed concrete, all dead, live, self and superimposed load.
Form coating compounds shall be those that do not stain bond or adversely affect the concrete or curing.

Yüklə 475,5 Kb.

Dostları ilə paylaş:
1   ...   47   48   49   50   51   52   53   54   ...   249




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin