2.6.8.2 ROADS MAINTENANCE
|
|
|
DRAFT MAINTENANCE PLAN 2011
|
|
|
|
Total Km
|
891.60
|
|
|
Budget Needed
|
R 4,458,000.00
|
|
|
|
|
|
Ward
|
Road Name
|
Activity Description
|
Length Km
|
26
|
Qinqana to Gongco
|
Wet Grading and Compaction
|
5.50
|
|
Shimrha to Botwe
|
Wet Grading and Compaction
|
5.00
|
|
Mantyi to Ngqatyane
|
Wet Grading and Compaction
|
6.00
|
|
Madwaleni to Khosani
|
Wet Grading and Compaction
|
6.00
|
|
Mphafeni to Manaleni
|
Wet Grading and Compaction
|
3.50
|
|
|
Sub-total
|
26.00
|
24
|
Qhingqala
|
Wet Grading and Compaction
|
6.00
|
|
Shixini
|
Wet Grading and Compaction
|
2.00
|
|
Phathilizwe
|
Wet Grading and Compaction
|
8.00
|
|
Xonyeni
|
Wet Grading and Compaction
|
6.00
|
|
Mhlabulungile
|
Wet Grading and Compaction
|
5.00
|
|
Upper Gwadu
|
Wet Grading and Compaction
|
3.50
|
|
Nombembe
|
Wet Grading and Compaction
|
2.00
|
|
Lubomvini
|
Wet Grading and Compaction
|
8.00
|
|
Jojweni
|
Wet Grading and Compaction
|
6.00
|
|
Nkelekete
|
Wet Grading and Compaction
|
8.00
|
|
Ntilini
|
Wet Grading and Compaction
|
8.10
|
|
|
Sub-total
|
62.60
|
23
|
Sponono
|
Wet Grading and Compaction
|
2.50
|
|
Nebelele
|
Wet Grading and Compaction
|
5.00
|
|
Rhafani
|
Wet Grading and Compaction
|
2.00
|
|
Bokweni
|
Wet Grading and Compaction
|
2.00
|
|
Mhlahlane
|
Wet Grading and Compaction
|
3.00
|
|
Old Qwaninga
|
Wet Grading and Compaction
|
3.00
|
|
Manxiwa
|
Wet Grading and Compaction
|
2.00
|
|
Mntonga to Mantlaneni
|
Wet Grading and Compaction
|
6.00
|
|
Ngxutyana JSS
|
Wet Grading and Compaction
|
2.00
|
|
Msintsini to Ngcizela
|
Wet Grading and Compaction
|
3.00
|
|
Nohantam line
|
Wet Grading and Compaction
|
2.50
|
|
Jotela
|
Wet Grading and Compaction
|
5.00
|
|
Folokwe
|
Wet Grading and Compaction
|
5.00
|
|
Zwelinzima JSS
|
Wet Grading and Compaction
|
2.00
|
|
|
Sub-total
|
45.00
|
22
|
KwaMacinga to Maxixibeni
|
Wet Grading and Compaction
|
5.00
|
|
Nocwane Store to Project
|
Wet Grading and Compaction
|
2.50
|
|
KwaVenge to Nkatha
|
Wet Grading and Compaction
|
11.00
|
|
|
Sub-total
|
18.50
|
21
|
All covered on Voting Station roads.
|
|
|
20
|
Khangelani Cafe to Bhula
|
Wet Grading and Compaction
|
15.00
|
|
Phokoloshe to Gobizembe
|
Wet Grading and Compaction
|
20.00
|
|
Dingata to Mbanyana
|
Wet Grading and Compaction
|
15.00
|
|
Nkanya to Mabholobela
|
Wet Grading and Compaction
|
15.00
|
|
Makhamese to Lalini
|
Wet Grading and Compaction
|
15.00
|
|
Haven to Geya
|
Wet Grading and Compaction
|
15.00
|
|
Geya to Xeni
|
Wet Grading and Compaction
|
5.00
|
|
Hobeni to Thembani
|
Wet Grading and Compaction
|
4.00
|
|
Hobeni to Ngxabane
|
Wet Grading and Compaction
|
10.00
|
|
Rebeshani to Mangqosini
|
Wet Grading and Compaction
|
5.00
|
|
Hobeni to Mdeni
|
Wet Grading and Compaction
|
7.00
|
|
Mdeni to Mncwana
|
Wet Grading and Compaction
|
5.00
|
|
Makhameso to Mbelu
|
Wet Grading and Compaction
|
6.00
|
|
Khangelani to Mafusini
|
Wet Grading and Compaction
|
6.00
|
|
Cwebe Road to Mampondweni
|
Wet Grading and Compaction
|
3.00
|
|
|
Sub-total
|
146.00
|
19
|
Mtonjeni to Nguberhamba SPS
|
Wet Grading and Compaction
|
20.00
|
|
Mpame road to KumkwanaSPS
|
Wet Grading and Compaction
|
5.00
|
|
Zitulele road to Lubanzi
|
Wet Grading and Compaction
|
7.00
|
|
|
Sub-total
|
32.00
|
18
|
|
Wet Grading and Compaction
|
15.00
|
|
Thelekhulu to Mncwasa river
|
Wet Grading and Compaction
|
5.00
|
|
Bafazi to Nditya
|
Wet Grading and Compaction
|
2.00
|
|
|
Sub-total
|
22.00
|
17
|
Tafalehashe to Delingubo
|
Wet Grading and Compaction
|
5.20
|
|
Ntlonyane to Mtshekelweni
|
Wet Grading and Compaction
|
5.00
|
|
Zembe to Bufumba
|
Wet Grading and Compaction
|
5.20
|
|
Kulohesha to Sidabekweni
|
Wet Grading and Compaction
|
4.80
|
|
Mqhele to Mrhabe
|
Wet Grading and Compaction
|
4.20
|
|
Mqhele Jss
|
Wet Grading and Compaction
|
0.50
|
|
Vulindaba
|
Wet Grading and Compaction
|
0.50
|
|
Mpakama
|
Wet Grading and Compaction
|
0.30
|
|
|
Sub-total
|
25.70
|
16
|
Bovane Clinic to Bumbane
|
Wet Grading and Compaction
|
3.00
|
|
Mount Pleasant to Madwaleni
|
Wet Grading and Compaction
|
3.00
|
|
Shelton to Pokoloshe
|
Wet Grading and Compaction
|
3.00
|
|
Shelton to Gwebizembe
|
Wet Grading and Compaction
|
4.00
|
|
Gwebindlala JSS to Mwana
|
Wet Grading and Compaction
|
1.50
|
|
|
Sub-total
|
14.50
|
15
|
Nkentshu to Tandiwe
|
Wet Grading and Compaction
|
7.00
|
|
Dabane to Lalini
|
Wet Grading and Compaction
|
2.20
|
|
Nqabayi to Sarhili
|
Wet Grading and Compaction
|
5.00
|
|
|
Sub-total
|
14.20
|
14
|
Bunga to Dalukhanyo
|
Wet Grading and Compaction
|
7.00
|
|
Ndude to Mbashe
|
Wet Grading and Compaction
|
2.00
|
|
Ndude to Lukhozana
|
Wet Grading and Compaction
|
2.00
|
|
Lukhozana to Upper Mbangcolo
|
Wet Grading and Compaction
|
3.00
|
|
Mtshazi SPS to Mndundu JSS
|
Wet Grading and Compaction
|
12.00
|
|
|
Sub-total
|
26.00
|
13
|
Majavu to Melitafa
|
Wet Grading and Compaction
|
20.00
|
|
Kasa to Riverview
|
Wet Grading and Compaction
|
20.00
|
|
Fameni to Cuntsula
|
Wet Grading and Compaction
|
15.00
|
|
Elliotdale to Technical
|
Wet Grading and Compaction
|
2.00
|
|
Majavu to Ncihana
|
Wet Grading and Compaction
|
3.00
|
|
Elliotdale to Ncihana JSS
|
Wet Grading and Compaction
|
6.00
|
|
Gwenteshe Junction to Makhamisa
|
Wet Grading and Compaction
|
5.00
|
|
Makhamisa shop to Mhlanga
|
Wet Grading and Compaction
|
10.00
|
|
Bhengu to Velelo
|
Wet Grading and Compaction
|
5.00
|
|
Magiqweni to Fameni Project
|
Wet Grading and Compaction
|
2.50
|
|
Mgwede to Phesheya Komnyama
|
Wet Grading and Compaction
|
6.00
|
|
|
Sub-total
|
94.50
|
12
|
Gxaka Gxaka
|
Wet Grading and Compaction
|
5.00
|
|
Fort Malan JSS
|
Wet Grading and Compaction
|
5.00
|
|
|
Sub-total
|
10.00
|
11
|
Ncedana to Mbethe
|
Wet Grading and Compaction
|
5.00
|
|
Pagasini
|
Wet Grading and Compaction
|
5.00
|
|
Dadamba to Matanzima
|
Wet Grading and Compaction
|
6.00
|
|
Dadamba to Gwabe
|
Wet Grading and Compaction
|
6.00
|
|
|
Sub-total
|
22.00
|
10
|
Bomela to Mzimkhulu
|
Wet Grading and Compaction
|
5.00
|
|
Mbukuqe to taleni JSS
|
Wet Grading and Compaction
|
5.00
|
|
Ntlabane to Kulokhala
|
Wet Grading and Compaction
|
5.00
|
|
Ntlabane Junction to Ntlabane
|
Wet Grading and Compaction
|
5.00
|
|
|
Sub-total
|
20.00
|
9
|
Murumuru to Mabheleni
|
Wet Grading and Compaction
|
4.00
|
|
|
Sub-total
|
4.00
|
8
|
Mpini to Enweleni
|
Wet Grading and Compaction
|
4.00
|
|
Chachazele to Vulingcobo
|
Wet Grading and Compaction
|
1.00
|
|
Maqundeni to Chaphaza
|
Wet Grading and Compaction
|
6.00
|
|
Stiyana to Khanya
|
Wet Grading and Compaction
|
3.00
|
|
Stishini to Kreqweni
|
Wet Grading and Compaction
|
11.00
|
|
Qombe to Gqubeni
|
Wet Grading and Compaction
|
4.00
|
|
Cerhu to Sibane
|
Wet Grading and Compaction
|
11.00
|
|
|
Sub-total
|
40.00
|
7
|
Mazwayi to Mabheleni
|
Wet Grading and Compaction
|
5.00
|
|
Komkhulu to Ezithenjini
|
Wet Grading and Compaction
|
6.00
|
|
Esihlabeni to Gungululu
|
Wet Grading and Compaction
|
6.70
|
|
|
Sub-total
|
17.70
|
6
|
Mhuku to Njemane
|
Wet Grading and Compaction
|
8.00
|
|
Thembalethu to Bekizulu
|
Wet Grading and Compaction
|
5.00
|
|
Lota store to Mlondzi
|
Wet Grading and Compaction
|
5.00
|
|
Mlondzi to Masango
|
Wet Grading and Compaction
|
2.00
|
|
N2 to Nkawukazi
|
Wet Grading and Compaction
|
3.00
|
|
Nkawukazi to Mantshilibeni
|
Wet Grading and Compaction
|
3.00
|
|
Nywara to Mhuku
|
Wet Grading and Compaction
|
5.00
|
|
Harmanas to Makinana
|
Wet Grading and Compaction
|
2.00
|
|
Mlonzi to Zimlindile SPS
|
Wet Grading and Compaction
|
2.00
|
|
Singeni to Makhobokeni
|
Wet Grading and Compaction
|
5.00
|
|
Ngqokweni to Esingeni
|
Wet Grading and Compaction
|
3.00
|
|
Nqabane store to Mabheleni
|
Wet Grading and Compaction
|
3.00
|
|
|
Sub-total
|
46.00
|
5
|
Mazizini
|
Wet Grading and Compaction
|
4.00
|
|
Vinindwa
|
Wet Grading and Compaction
|
4.00
|
|
Vonqo
|
Wet Grading and Compaction
|
5.00
|
|
Bolotwa
|
Wet Grading and Compaction
|
3.50
|
|
Nyakatha
|
Wet Grading and Compaction
|
4.00
|
|
Mazizini to Vinindwa
|
Wet Grading and Compaction
|
5.00
|
|
Nyakatha to Qolweni
|
Wet Grading and Compaction
|
4.50
|
|
(DR 08279) Sihlabeni to Bolotwa
|
Wet Grading and Compaction
|
5.00
|
|
Mbanga
|
Wet Grading and Compaction
|
4.50
|
|
Bangweni
|
Wet Grading and Compaction
|
2.50
|
|
|
Sub-total
|
42.00
|
4
|
Mbewuleni
|
Wet Grading and Compaction
|
3.00
|
|
Timane Junction to Gaxa JSS
|
Wet Grading and Compaction
|
9.80
|
|
Gxara to Mangwevini
|
Wet Grading and Compaction
|
5.00
|
|
Sinqumeni to Nyakatha JSS
|
Wet Grading and Compaction
|
5.00
|
|
Zithenjini Junction to Munyu JSS
|
Wet Grading and Compaction
|
5.00
|
|
|
Sub-total
|
27.80
|
3
|
Qhorha
|
Wet Grading and Compaction
|
5.00
|
|
Mahliwane
|
Wet Grading and Compaction
|
2.00
|
|
Gwadana Mission to Ndenga
|
Wet Grading and Compaction
|
4.50
|
|
Gwadana Tribal Authority
|
Wet Grading and Compaction
|
8.00
|
|
Gwadana Mission to Manya
|
Wet Grading and Compaction
|
3.50
|
|
Mpepheni to Qelane
|
Wet Grading and Compaction
|
4.00
|
|
Mpepheni to Tyholomi
|
Wet Grading and Compaction
|
6.00
|
|
Lusizini to Zimpuku
|
Wet Grading and Compaction
|
3.00
|
|
|
Sub-total
|
36.00
|
2
|
Xeni to upper Colosa
|
Wet Grading and Compaction
|
20.00
|
|
|
Sub-total
|
20.00
|
1
|
Doti Access Road
|
Wet Grading and Compaction
|
7.00
|
|
Govan Mbeki to Doti
|
Wet Grading and Compaction
|
3.00
|
|
Dutywa to Govan Mbeki
|
Wet Grading and Compaction
|
5.00
|
|
Govan Mbeki to Phola Park
|
Wet Grading and Compaction
|
2.00
|
|
Govan Mbeki Township streets
|
Wet Grading and Compaction
|
15.00
|
|
Whack Street
|
Wet Grading and Compaction
|
2.40
|
|
Maduna Street
|
Wet Grading and Compaction
|
2.00
|
|
Streetfield
|
Wet Grading and Compaction
|
3.00
|
|
Stanford street
|
Wet Grading and Compaction
|
3.00
|
|
CBD Roads
|
Wet Grading and Compaction
|
19.10
|
|
Dutywa to New Rest
|
Wet Grading and Compaction
|
2.10
|
|
Dutywa to GPO
|
Wet Grading and Compaction
|
1.50
|
|
Extension 8 Access Roads
|
Wet Grading and Compaction
|
14.00
|
|
|
Sub-total
|
79.10
|
|
|
Total
|
891.60
|