JULY-PRE-PLANNING PHASE
|
ITEM. NO.
|
ACTIVITIES
|
NATURE OF THE MEETING
|
DATE
|
1.
|
Reviewal of the PMS framework plan
|
None
|
N/A
|
2.
|
Preparation of the IDP process plan
|
None
|
N/A
|
3.
|
Adoption of the IDP/Budget process and Framework plans
|
Special Council Meeting
|
08/2010
|
4.
|
Advertising of the framework plan
|
None
|
|
5.
|
Presentation of the project plans
|
Cluster meetings
|
|
6.
|
PMS reporting (2007/2008 reports)
|
Cluster meetings
|
|
7.
|
Preparations for the IDP launch
|
IDP/Budget steering committee
|
|
AUGUST-PLANNING PHASE
|
ITEM. NO.
|
ACTIVITIES
|
NATURE OF THE MEETING
|
DATE
|
1.
|
PMS reporting (Project progress)
|
Cluster meetings
|
2010
|
2.
|
Launch of the IDP
|
IDP rep. forum
|
20 August 2010
|
3.
|
Preparations for Community Based Planning
|
IDP/Budget steering committee
|
27 August 2010
|
|
|
|
|
SEPTEMBER-PLANNING PHASE
|
ITEM. NO.
|
ACTIVITIES
|
NATURE OF THE MEETING
|
DATE
|
1.
|
PMS reporting (Project progress)
|
Cluster meetings)
|
9th and 10th September 2010
|
2.
|
Reviewal of sector plans
|
None
|
01st to 30th September 2010
|
3.
|
Community Based Planning starts
|
Village and Ward meetings
|
01st to 30th September 2010
|
OCTOBER-ANALYSIS PHASE
|
ITEM. NO.
|
ACTIVITIES
|
NATURE OF THE MEETING
|
DATE
|
1.
|
PMS reporting (Project progress)
|
Cluster meetings
|
07th and 08th October 2010
|
2.
|
Preparations for the analysis phase
|
IDP steering committee
|
15/10/2010
|
3.
|
Considering reports from the wards (CBP)
|
IDP steering committee
|
15/10/2010
|
4.
|
Sector plan reports from the head of departments
|
IDP steering committee
|
15/10/2010
|
5.
|
Collecting of information from various sources by sectional heads.
|
None
|
01st to 31st October 2010
|
NOVEMBER-ANALYSIS PHASE
|
ITEM. NO.
|
ACTIVITIES
|
NATURE OF THE MEETING
|
DATE
|
1.
|
Presentation of the Situational Analysis to the steering committee
|
Steering Committee meeting
|
05 November 2010
|
2.
|
PMS reporting (Project progress)
|
Cluster meetings
|
11th and 12th November 2010
|
3.
|
Presentation of situational analysis
|
Cluster meetings
|
11th and 12th November 2010
|
4.
|
Reporting on Ward priorities
|
Cluster Meetings
|
11th and 12th November 2010
|
5.
|
Presenting the Situational Analysis and Ward priorities to Rep forum
|
IDP representative forum meeting
|
20 November 2010
|
DECEMBER-STRATEGIES PHASE
|
ITEM. NO.
|
ACTIVITIES
|
NATURE OF THE MEETING
|
DATE
|
1.
|
Receiving reports for the strategic session meeting from the section heads
|
None
|
04/12/2010
|
2.
|
Considering reports for strategic session
|
IDP/Budget steering committee
|
09/12/2010
|
JANUARY-STRATEGIES PHASE
|
ITEM. NO.
|
ACTIVITIES
|
NATURE OF THE MEETING
|
DATE
|
1.
|
PMS reporting (Project progress)
|
Cluster meetings
|
20th and 21st January 2011
|
2.
|
Final preparations for the Strategic session
|
IDP steering Committee Meeting
|
22/01/2011
|
3.
|
Reviewal of the strategies and objectives, setting up new objectives and strategies based on new priorities
|
Strategic session meeting
|
14th and 15th February 2011
|
FEBRUARY-STRATEGIES PHASE
|
ITEM. NO.
|
ACTIVITIES
|
NATURE OF THE MEETING
|
DATE
|
1.
|
PMS Reporting
|
Cluster meetings
|
17th and 18th February 2011
|
2.
|
Presentation of the strategies and objectives by cluster heads
|
Cluster Meetings
|
17th and 18th February 2011
|
3.
|
Determining projects based on the objectives and strategies
|
Cluster Meetings
|
17th and 18th February 2011
|
4.
|
Considering projects from other sector departments
|
IGR forum meetings
|
22nd to 26th February 2011
|
MARCH-PROJECTS PHASE
|
ITEM. NO.
|
ACTIVITIES
|
NATURE OF THE MEETING
|
DATE
|
1.
|
Presentation of the draft IDP and Budget to steering committee
|
IDP/Budget steering committee
|
07 March 2011
|
2.
|
PMS reporting (project progress)
|
Cluster meetings
|
10th and 11th of March 2011
|
3.
|
Presentation of the draft IDP to Rep. forum
|
IDP representative forum meeting
|
11 March 2011
|
4.
|
Presentation and approval of the draft IDP to and by council
|
Council Meeting
|
16 March 2011
|
5.
|
Advertising of the IDP, calling for public comments
|
None
|
17 March 2011
|
APRIL-APPROVAL PHASE
|
ITEM. NO.
|
ACTIVITIES
|
NATURE OF THE MEETING
|
DATE
|
1.
|
PMS reporting
|
Cluster meetings
|
07th and 08th April 2011
|
2.
|
Presentation of the IDP to the communities
|
IDP road shows
|
17 March to 08 April 2011
|
APRIL-APPROVAL PHASE
|
ITEM. NO.
|
ACTIVITIES
|
NATURE OF THE MEETING
|
DATE
|
1.
|
Looking at the comments from the roadshows
|
IDP Steering Committee Meeting
|
11/04/2011
|
2.
|
Presentation of the final draft IDP to steering committee
|
IDP Steering Committee meeting
|
18/04/2011
|
4.
|
Presentation of the final draft IDP to IGR
|
IGR
|
19/04/2011
|
5.
|
Presentation of the final draft IDP to rep forum
|
IDP representative forum
|
19/04/2011
|
6.
|
Approval of the final draft IDP by council
|
Council Meeting
|
20/04/2011
|
JUNE-APPROVAL PHASE
|
ITEM. NO.
|
ACTIVITIES
|
NATURE OF THE MEETING
|
DATE
|
1.
|
Printing of the IDP documents
|
None
|
N/A
|
2.
|
PMS reporting (Project progress)
|
Cluster meetings
|
09th and 10th June 2011
|
3.
|
Presentation of project plans
|
Cluster meetings
|
09th and 10th June 2011
|
4.
|
Presentation of the SDBIP and Municipal Scorecard to council
|
Council meeting
|
24 June 2011
|
PROCESS
|
LEGISLATIVE REQUIREMENTS
|
RESPONSIBILITY
|
TIME FRAME
|
Implementation of the budget 2009/10 financial year
Start with the preparation of the next budget and review previous year’s budget checklist.
|
MFMA s53
|
Municipal Manager
Mayor
|
01 July 2010
31 July 2010
|
Mayor tables in council the schedule of key deadlines setting the time table for: preparing, tabling and approving the budget, reviewing the IDP and budget related policies and consultation processes at least 10 months before the start of the budget year.
Mayor establishes committees and consultation forums for the budget process
|
MFMA s21,22,23 and MSA s34, chapter 4
|
Mayor
|
30 August 2010
|
Council through the IDP review process determines strategic objectives for service delivery and development for next three –year budget including review of district, provincial and national government sector and strategic plans of Mbhashe Municipality.
|
National Treasury recommendation
|
Council
|
September -October 2010
|
Submit quarterly report to council on the implementation of the budget and financial affairs of the municipality
|
MFMA s 52 (d)
|
Mayor
|
10 October 2010
|
Council finalises tarrifs (rates and service charges) policies for the next financial year
|
MSA s 74,75
|
Council
|
November –December 2010
|
Assess the performance of the municipality in the first six months of the financial year
|
MFMA s 72
|
Municipal Manager
|
25 January 2011
|
Submit mid-year performance assessment report to council
|
MFMA s 54 (1) (f)
|
Mayor
|
31 January 2011
|
Review proposed national and provincial allocations and projects for the next three years information which will be made available
|
MFMA s36
|
Municipal Manager
|
25 January 2011
|
Table the adjustments budget for 2009/10 if necessary
|
MFMA 72 (3)
|
Mayor
|
February 2011
|
Annual budget tabled at council at least 90 days before the start of the budget year.
|
MFMA 16 (2)
|
Mayor
|
30 April 2011
|
Public hearings on the budget and council debate.
Council consider views of the local community, National Treasury, provincial Treasury and other organs of the state.
Mayor to be provided with an opportunity to respond to submissions during consultation and table amendments for council consideration.
Council to consider approval of budget and plans at least 30 days before start of budget year.
|
MSA Chapter 4 as amended
MFMA 23(1)
MSA Chapter 4 as amended
MFMA 24(1)
|
Mayor
Council
Mayor
Council
|
May 2011
May 2011
May 2011
30 May 2011
|
Consider approval of annual budget 2010/11 by resolution, setting taxes and tarrifs.
Approving changes to IDP and budget related policies.
Approving measurable performance objectives for revenue by source and expenditure by vote before start of budget year
|
MFMA s 16,24,26,53
|
Council
|
June 2011
|
Submit Service delivery implementation plan (SDBIP) 2010/11 within 14 days after approval of the budget
|
MFMA 69(3)
|
Municipal Manager
|
14 June 2011
|
Approval of Service delivery implementation plan (SDBIP) 2010/11 within 28 days after the approval of the budget and ensure that annual performance contracts are included in accordance with s 57(2) of the MSA.
Ensure that the annual performance agreements are linked to the measurable performance objectives approved with the budget and SDBIP.
The mayor submits the approved SDBIP and performance agreements to council, MEC for Local Government and makes public within 14 days after approval.
|
MFMA s 53
MSA s38-45, 57(2)
|
Mayor
|
28 June 2011
|