Progress: On track
The foundations for the new Broxbourne White Water Canoe Centre were completed at the end of 2009. The embankments for the canoe course have been formed, the starting pool for the competition course (pictured) has been completed and the venue’s finish lake is being excavated. At Eton Dorney, work has concluded on the enhancements necessary for the Games, including a new 50m-span finishing line bridge that was lifted into place in January 2010.
Planning permission for the temporary facilities for the Games at the Royal Artillery Barracks has been granted.
Milestone 8
More than half of the new bridges and underpasses will be complete and parts of the Olympic Park Loop Road in operation. Planting will have begun across the Park.