Envestra's revised proposal forecast total net capex of $521.8 million ($2011, escalated direct costs, including NMF) for the 2013–17 access arrangement period. This is a reduction of $243.1 million ($2011, escalated direct costs, including NMF) from Envestra's initial proposal of $764.9 million ($2011, escalated direct costs, including NMF). The major differences between Envestra's initial and revised proposal are:
Mains—Envestra revised its volumes down from an initial volume of 636 kilometres to 475 kilometres subject to the provision of the pass through. Envestra proposed a new unit rate methodology, which resulted in a reduced average unit rate.
Connections—Envestra proposed revised unit rates based on the weighted average of 2010/11 and 2011/12 historical unit rates. Envestra no longer proposed adjustments to its unit rates for increases driven by changes in the regions where connections are occurring and newer contracts.
Meters—Envestra proposed a new unit rate forecast methodology based on the weighted average of 2010/11 and 2011/12 historical unit rates. This differed from the bottom-up forecast it provided in its initial proposal.
Augmentation—Envestra altered the scope of its Dandenong to Crib Point augmentation, revising the expenditure down from $18.3 million ($2011, unescalated direct costs, excluding overheads and NMF) to $10.8 million ($2011, unescalated direct costs, excluding overheads and NMF).
Other non-demand—Envestra adopted the AER's draft decision on 14 of its other non-demand projects. Envestra re-submitted 4 other non-demand projects, which the AER did not accept in its draft decision.
Overheads—Envestra adopted the AER's draft decision on overheads, leading to a downwards revision of $49.4 million ($2011).
Table 4.6 Victorian network - Envestra revised proposal of conforming capital expenditure 2013–17 ($million 2011, escalated direct costs, including NMF)
Envestra's revised proposal forecast total net capex of $6.7 million ($2011, escalated direct costs, including NMF) for the 2013–17 access arrangement period. This is a reduction of $1.5 million ($2011, escalated direct costs, including NMF) from Envestra's initial proposal of $8.2 million ($2011, escalated direct costs, including NMF). The substantial changes from its initial proposal are the same as for the Victorian network.
Table 4.7 Albury network - Envestra revised proposal of conforming capital expenditure 2013–17 ($million 2011, escalated direct costs, including NMF)