Spatial positioning of sidewall stations in a narrow tunnel environment: a safe alternative to traditional mine survey practice


Proposed guidelines for the establishment and propagation of a sidewall station survey network



Yüklə 2 Mb.
səhifə33/57
tarix28.07.2018
ölçüsü2 Mb.
#60866
1   ...   29   30   31   32   33   34   35   36   ...   57

8.3. Proposed guidelines for the establishment and propagation of a sidewall station survey network

A high level flow diagram, shown in

Error: Reference source not found, illustrates the process of establishing a survey network that is be used to provide an outline for the preparation of the survey guidelines.



Figure . A high level flow diagram of the survey process. [180]



8.4. Phase 1. Preparation


The careful planning of a survey is critical to the success of a surveyor when installing survey control, in order to evaluate the factors that will have an impact on the physical safety of the survey crew as well as the integrity of the survey network. The main factor linked to the successful and accurate completion of a survey task is the efficient communication between surveyor, supervisor, crew and production crews. A lack of understanding and co-operation between any of these parties will impact negatively on the success and accuracy of a survey.

      1. Safety considerations

On most South African mines it is standard practice to perform a risk assessment of the work to be performed during a shift. Such risk assessment is essential to ensure that the risk exposure is minimized or mitigated as far as possible. Aspects of risks recommended for evaluation are listed in the following risk assessment:



Table . Risk analysis for the preparation phase of installing sidewall stations.

Risk

Hazard

Contributing factors

Mitigating Actions

Potential injury to survey crew or survey instrument


Unfamiliarity with site and procedures
Unfamiliarity with survey method


No or limited communication with supervisor, crew and production personnel
Lack of training, “buy-in” in method


Proper , survey related induction
Training
Change management

Potential injury to survey crew or survey instrument

Moving Equipment

Rail bound equipment
Trackless equipment
Conveyor Belts
Winch / Scraper
Persons carrying drill steel, timber and rails or dragging cables and pipes

Wear correct PPE (reflective)
Obtain permission to enter area
Lock-out, Stop or Barricade working area
Communicate needs with production supervisor


Potential injury to survey crew or survey instrument

Slip and Fall
Tripping over material and equipment

Footwall conditions: Loose material, Mud or water accumulation
Rails and sleepers
Tripod instable as a result of footwall conditions


Wear correct PPE
Take care when moving around site
Ensure tripod is stable
Lighting

Potential injury to survey crew or survey instrument

Ground Conditions

Hangingwall
Sidewall
Geological conditions

Obtain permission to enter area
Request inspection and barring by appointed person


Potential injury to survey crew or survey instrument

Environment

Gas present / Fiery mine
Noise
Illumination
Dust
Water vapour
Fumes (Blast / exhaust)
Laser light emission
Thermal (too hot or cold)
Strong ventilation

Intrinsically safe equipment / welding permission (site specific)
Wear correct PPE
Additional lights must be used where required
Ensure prism and instrument is acclimatized
Use radios or pre-arranged hand or light signals
Laser pointer of instrument to be aimed with care and non-survey personnel warned of the danger

Integrity of survey network compromised

Inadequate training and education

Not familiar with survey fundamentals
Not familiar with instrument or software
Not familiar with observation protocol


Ensure all surveyors have been adequately trained in all aspects of the survey required
Establish minimum level of education

Integrity of survey network compromised

Communication

No communication between survey crew and production crew

Communicate job requirements to survey and production crew


Potential injury to survey crew or survey instrument
Potential error in survey propagated

Production pressure

No communication between survey crew and production crew

Obtain permission to enter area
Ensure the job is discussed and cleared with the production supervisor


[159]

Each of these risks should be evaluated and discussed to understand how the risk can be avoided, mitigated or reduced. Such risk assessment will have to meet industry specific specifications which will vary from operation to operation.



      1. Planning of the network

A factor often overlooked in the establishment and extension of a survey network on a mine is the planning and error analysis of a survey network. When a new mine is planned and developed, care should be taken to ensure the accuracy of the shaft sinking and transfer of the meridian into the underground workings. It is recommended that the survey network should be planned and evaluated with the same care prior to a network being established, and should include the process of estimating extent of error propagation, the required accuracy of the networks, the placement of baselines, control points and check surveys. The boundaries between primary, secondary and tertiary survey networks with their individual accuracy requirements should be clearly defined and planned. The parameters decided upon can be dictated by corporate standards established from the results of existing survey networks within the domain of the specific mining industry and the results of any check surveys. The results obtained from the final phase of the process of check surveying are to be used to fine tune the next iteration of survey planning.


The financial impact of the accuracy of the survey model surveying on an ore reserve is represented as a cause and effect diagram in Figure . The diagram should be read from the bottom of the diagram.


Figure . A cause and effect diagram of survey information. [181]


      1. Equipment used

The equipment used to install sidewall survey stations is similar to the equipment used for conventional hangingwall station surveys. The equipment list described in Chapter 6 and attached as Appendix 10.. This list describes the recommended equipment to be used in a survey station installation. In general the type of equipment will be dictated by corporate and site-specific specifications. Such specifications may place restrictions on using non-intrinsically-safe battery operated equipment in areas where gas may be accumulated or where the area is defined as a “fiery mine”. The use of ladders or equipment manufactured out of aluminium is restricted in mines classified as “fiery mines” due to the inherent risk of thermite reactions that may occur between oxidized metal and aluminium.


Specific equipment requirements will be discussed in the Standard Operating Procedures in Appendix 7. Regardless of the make of instrument selected on site the specifications of the instrument used must at least conform to the following minimum requirements of 5 second angular accuracy and measuring accuracy of at least 2.5mm ± 2 ppm. Instruments should have the ability to be “field serviced” by the user in the case where minor corrections or adjustments are required to be made to the instrument. These adjustments must include EDM calibration, scale and ppm settings. In the case of deep level mines with significant difference in pressure between surface and the underground levels a mine specific standard must be developed to address the setting of scale and PPM factors per level or to maintain the same setting for the entire site.
Prisms are in general not serviced or maintained to the same degree as a survey instrument, it is essential that the condition of all prisms be checked before commencing a survey task. It is recommended that the prism optical centres be checked to coincide with the reference centres of the prism housing before being used underground. Large round prisms are more likely to have a discrepancy between the observed optical centre and the true optical centre. Where possible then mini-prisms designed for accurate work should be used. Prism attachments must be checked against the manufacturer’s specified dimensions. It has been found that manufactured attachments do not always comply with the designed dimensions and specifications.

      1. Personnel requirements

The level of training and education of the surveyor, survey crew and in the case of an operator (mining person) must also be taken into consideration. Although modern instruments are mostly intuitive in the guidance of an operator through a specific observation protocol, all operators must be trained in the theoretical aspect of making a resection observation. It has been found that in some cases days are spent in ensuring that a new employee is inducted into the safety aspects of operating underground, but that little time is spent on ensuring that the surveyor understands the observation protocol and instruments used on a specific site. In the case where sidewall survey stations are to be used as an alternative method of surveying it is advisable to introduce the method using proper change management procedures to ensure “buy-in” and compliance with the new method. The following generic hazards have been identified in the following risk assessment:

Table . Risk analysis of equipment use during the installation of sidewall stations.

Risk

Hazard

Contributing factors

Mitigating Actions

Survey results do not comply with minimum standards of accuracy

Off-line mining
Mine layout must be changed
Unplanned breakthrough
Mis-holing of excavations
Damage to structural design (pillars)
Error Propagation

Instrument settings:
Prism constant
Scale factor
EDM calibration
Operator skill level


Regular calibration
Check against baseline
PPM setting per level or standard for mine
Operator training

Damaged survey reference survey stations

Off-line mining
Mine layout must be changed
Unplanned breakthrough
Mis-holing of excavations
Damage to structural design (pillars)


Prism affected by dust or vapour
Blast damage
Theft or intentional vandalism
Damage during installation
Damage by mobile equipment
Rock movement or scaling due to pressure or geological factors


Ensure prisms are clean
Use non-metal survey stations
Ensure stations are placed in area where probability of damage is minimized
Protect station with rubber mat or similar cover

Damage to instrument

Loss of production
Financial loss
Loss of adjustment and calibration

Slip and Fall (floor conditions)
Moving personnel and machinery
Instrument not fastened to tripod
Damaged tripod
Incorrect tripod (head size)


Survey fundamental protocol
Communication between crew and production personnel
Barricade, lock-out procedures

Potential injury to survey crew

Hand tools

Drill can injure operator

Hammer can injure survey crew member or survey station if improperly used.



Equipment in good condition
Training in use of equipment
Use expanding bolt type plug

Instrument not adjusted correctly

Incorrect scale or PPM setting
Incorrect mask for capturing observations

Lack of standardized PPM settings
User not allowed to make adjustments

Training in use of equipment
Regular calibration
Check against baseline
PPM setting per level or standard for mine

[159]

Yüklə 2 Mb.

Dostları ilə paylaş:
1   ...   29   30   31   32   33   34   35   36   ...   57




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin